5050 N STROHM AVE 91601
Certificate Information: 5050 N STROHM AVE 91601
- Application / Permit
- 21014-20000-02703
- Plan Check / Job No.
- B21VN06715
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 20' X 24'-9" ADDITION AND REMODEL TO (E) SFD. ALL WORK PER WFPP.
- Permit Issued
- Issued on 7/14/2021
- Issuing Office
- Current Status
- CofO Issued on 1/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/2/2021 | RAPHAEL ROSAS |
| Corrections Issued | 6/3/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 7/2/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 7/6/2021 | APPLICANT |
| Issued | 7/14/2021 | APPLICANT |
| CofO in Progress | 1/13/2023 | JOHN HAYES |
| CofO Issued | 1/19/2023 | MICHAEL SMITH |
| Permit Finaled | 1/19/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/28/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/29/2021 | CARLOS AGUILERA |
| Tract Map conditions | Cleared | 6/29/2021 | DANG NGUYEN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/20/2021 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 9/20/2021 | Conditional Approval | DANIEL DREW |
| BUILDING-Rough-Frame | 9/29/2021 | Partial Approval | DANIEL DREW |
| Green Building Rough | 9/29/2021 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 10/1/2021 | Partial Inspection | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Partial Inspection | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 11/3/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Rough | 11/3/2021 | Approved | DANIEL DREW |
| Green Building Rough | 11/3/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 11/3/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 11/3/2021 | Approved | DANIEL DREW |
| Insulation | 11/8/2021 | Approved | CALEB MEISTER |
| Drywall Nailing | 11/12/2021 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 11/23/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 11/23/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 12/6/2021 | Corrections Issued | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 12/9/2021 | Approved | ASHLEY THOMPSON |
| Shower Pan | 12/9/2021 | Approved | ASHLEY THOMPSON |
| Final | 1/18/2022 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 1/18/2022 | Approved | DAVID MATSON |
| Green Building Final | 1/18/2022 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 1/18/2022 | SGSOV Approved | DAVID MATSON |
| Smoke Detectors | 1/18/2022 | Corrections Issued | DAVID MATSON |
| Final | 2/8/2022 | Corrections Issued | MISAEL ESPARZA |
| Smoke Detectors | 2/8/2022 | Approved | MISAEL ESPARZA |
| Final | 3/16/2022 | Not Ready for Inspection | DAVID MATSON |
| Final | 1/10/2023 | OK to Issue CofO | JOHN HAYES |