15046 W TUBA ST 91345

Certificate Information: 15046 W TUBA ST 91345

Application / Permit
21014-20000-02695
Plan Check / Job No.
B21VN06703
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION IRREGULAR SHAPED ( 25'-10" X 24'-0 ) TO EX. SFD FOR MASTER BEDROOM/ BATHROOM/ CLOSET. ENCLOSE 7'-10" X 7'-0" FRONT PORCH. WORK PER WFPP.
Permit Issued
Issued on 8/16/2022
Issuing Office
Valley
Current Status
CofO Issued on 12/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/8/2021 APPLICANT
Assigned to Plan Check Engineer 6/9/2021 GURUNATH NESARAJAH
Corrections Issued 6/9/2021 GURUNATH NESARAJAH
Building Plans Picked Up 7/28/2021 APPLICANT
Plan Check Approved 8/16/2022 ROSENDO MEDINA
Issued 8/16/2022 APPLICANT
CofO in Progress 12/16/2023 ROBERT GOLD
CofO Issued 12/21/2023 RUBEN SALAS
Permit Finaled 12/21/2023 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 7/1/2022 ROMAN GUTIERREZ
Low Impact Development Cleared 7/15/2022 TA ANH
Roof/Waste drainage to street Cleared 8/2/2022 ROMAN GUTIERREZ
Sewer availability Cleared 8/15/2022 ROMAN GUTIERREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/8/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 9/16/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 9/16/2022 Partial Approval JENNIFER RABUCHIN
Insulation 9/20/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 9/23/2022 Partial Approval CALEB MEISTER
ELECTRICAL-Rough 10/14/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Approved JENNIFER RABUCHIN
Green Building Rough 10/14/2022 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 10/14/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 10/24/2022 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 11/28/2022 Partial Inspection JENNIFER RABUCHIN
Green Building Rough 11/28/2022 Corrections Issued JENNIFER RABUCHIN
Shower Pan 11/28/2022 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 2/22/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 2/22/2023 Corrections Issued JENNIFER RABUCHIN
Special/Order Compliance 2/22/2023 Corrections Issued JENNIFER RABUCHIN
Wood Frame 2/22/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/22/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/22/2023 Corrections Issued JENNIFER RABUCHIN
Final 6/22/2023 Corrections Issued JENNIFER RABUCHIN
Gas Test 6/22/2023 Corrections Issued JENNIFER RABUCHIN
Green Building Final 6/22/2023 Approved JENNIFER RABUCHIN
Green Building Rough 6/22/2023 Approved JENNIFER RABUCHIN
HVAC-Final 6/22/2023 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/22/2023 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/22/2023 SGSOV Not Ready JENNIFER RABUCHIN
Smoke Detectors 6/22/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 6/29/2023 Approved JENNIFER RABUCHIN
Final 6/29/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Final 6/29/2023 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/10/2023 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Final 8/15/2023 Approved ROBERT GOLD
Final 8/28/2023 OK to Issue CofO JENNIFER RABUCHIN