6450 N FAIR AVE 91606
Certificate Information: 6450 N FAIR AVE 91606
- Application / Permit
- 21014-20000-02692
- Plan Check / Job No.
- B21VN06697
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- PROPOSED 35'-7" x 30'-4" (691 S.F) IRREGULAR SHAPED ADDITION TO (E) SINGLE FAMILY DWELLING FOR NEW BEDROOM, BATHROOM, MASTER BEDROOM AND BATHROOM. ADD 20'-0" x 13'-6" ATTACHED PATIO COVER AT REAR. INTERIOR REMODEL TO CONVERT (E)BEDROOM INTO A STUDY ROOM AND STORAGE. " NFPA-13D FIRE SPRINKLERS THRU-OUT. "
- Permit Issued
- Issued on 8/6/2021
- Issuing Office
- Current Status
- CofO Issued on 1/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 7/3/2021 | SARKIS HARABEDIAN |
| Quality Review Completed | 7/9/2021 | STEVEN KIM |
| Plan Check Approved | 8/6/2021 | SARKIS HARABEDIAN |
| Issued | 8/6/2021 | APPLICANT |
| Building Plans Picked Up | 8/6/2021 | APPLICANT |
| CofO in Progress | 12/13/2022 | JOHN HAYES |
| Permit Finaled | 1/19/2023 | MICHAEL SMITH |
| CofO Issued | 1/19/2023 | MICHAEL SMITH |
| Permit Finaled | 1/19/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/12/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/13/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 7/22/2021 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 8/4/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/24/2021 | Not Ready for Inspection | DANIEL DREW |
| Footing/Foundation/Slab | 9/30/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 10/15/2021 | Partial Approval | DANIEL DREW |
| PLUMBING-Rough | 10/15/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2021 | Partial Approval | DANIEL DREW |
| ELECTRICAL-Rough | 12/22/2021 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Rough | 12/22/2021 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 12/22/2021 | Corrections Issued | MISAEL ESPARZA |
| Deputy Wood Construction | 12/29/2021 | Partial Approval | JOHN KIDWELL |
| BUILDING-Rough-Frame | 1/3/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 1/3/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 1/3/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 1/3/2022 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 1/14/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/14/2022 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 1/14/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 1/21/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 1/21/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 1/27/2022 | Partial Inspection | CALEB MEISTER |
| Drywall Nailing | 2/1/2022 | Approved | JENNIFER RABUCHIN |
| Final | 9/14/2022 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 9/14/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 9/14/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 11/9/2022 | Corrections Issued | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 11/9/2022 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 11/9/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 12/13/2022 | OK to Issue CofO | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Approved | JOHN HAYES |
| Smoke Detectors | 12/13/2022 | Approved | JOHN HAYES |