11671 W MARGATE ST 91601

Certificate Information: 11671 W MARGATE ST 91601

Application / Permit
21014-20000-02688
Plan Check / Job No.
B21VN06693
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION OF A BATHROOM TO THE (E) SFD.
Permit Issued
Issued on 7/2/2021
Issuing Office
Current Status
CofO Issued on 8/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/27/2021 APPLICANT
Assigned to Plan Check Engineer 6/1/2021 JESSE ARELLANO
Corrections Issued 6/1/2021 JESSE ARELLANO
Issued 7/2/2021 APPLICANT
Building Plans Picked Up 7/6/2021 APPLICANT
CofO in Progress 1/31/2022 MISAEL ESPARZA
Permit Finaled 8/6/2022 DEROLD HAUFF
CofO Issued 8/6/2022 DEROLD HAUFF
Permit Finaled 8/6/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/3/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/3/2021 CARLOS AGUILERA
Sewer availability Cleared 6/3/2021 CARLOS AGUILERA
Specific Plan Cleared 6/25/2021 ERIN NASH
Green Code Cleared 7/2/2021 JESSE ARELLANO

Contact Information

Contractor Pristine Construction Inc; Lic. No.: 939885-B 14320 VENTURA BL   #320    SHERMAN OAKS, CA 91423
Engineer Khansa,, Eyass Wafik; Lic. No.: C91758 2252 JOSIE AVE      LONG BEACH, CA 90815

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 10/13/2021 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 10/15/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 10/20/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Rough 11/2/2021 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/8/2021 Corrections Issued THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 11/12/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 11/29/2021 Conditional Approval THOMAS FINNILA
ELECTRICAL-Rough 11/29/2021 Corrections Issued THOMAS FINNILA
Green Building Rough 11/29/2021 Approved THOMAS FINNILA
HVAC-Rough 11/29/2021 Approved THOMAS FINNILA
MERV13>=Rough 11/29/2021 Approved THOMAS FINNILA
PLUMBING-Rough 11/29/2021 Approved THOMAS FINNILA
Insulation 12/3/2021 Approved THOMAS FINNILA
Drywall Nailing 12/13/2021 Approved ASHLEY THOMPSON
Shower Pan 12/13/2021 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 12/20/2021 Approved THOMAS FINNILA
BUILDING-Rough-Frame 1/27/2022 Approved MISAEL ESPARZA
Final 1/27/2022 OK to Issue CofO MISAEL ESPARZA
Footing/Foundation/Slab 1/27/2022 Approved MISAEL ESPARZA
Green Building Final 1/27/2022 Approved MISAEL ESPARZA
MERV13>=Final 1/27/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 1/27/2022 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 1/27/2022 Approved MISAEL ESPARZA