6036 N DENNY AVE 91606
Certificate Information: 6036 N DENNY AVE 91606
- Application / Permit
- 21014-20000-02683
- Plan Check / Job No.
- B21VN06683
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan. Convert Garage into Accessory Dwelling unit with small addition. per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 10/5/2022
- Issuing Office
- Current Status
- CofO Issued on 8/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2021 | MONICA RAMIREZ |
| Corrections Issued | 7/6/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 11/22/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 2/2/2022 | MONICA RAMIREZ |
| Plan Check Approved | 2/7/2022 | MONICA RAMIREZ |
| Issued | 10/5/2022 | APPLICANT |
| CofO in Progress | 5/24/2024 | JOSE AVILA |
| CofO Issued | 8/19/2024 | DANIEL ORRANTE |
| Permit Finaled | 8/19/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 8/18/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 8/18/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/29/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 10/5/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/31/2023 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 2/6/2023 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 2/16/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 2/22/2023 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2023 | Partial Approval | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/24/2023 | Not Ready for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 3/24/2023 | Corrections Issued | JOHN COLEMAN |
| Green Building Rough | 3/24/2023 | Not Ready for Inspection | JOHN COLEMAN |
| HVAC-Rough | 3/24/2023 | Corrections Issued | JOHN COLEMAN |
| PLUMBING-Rough | 3/24/2023 | Corrections Issued | JOHN COLEMAN |
| BUILDING-Rough-Frame | 4/4/2023 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 4/4/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 4/4/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 4/4/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 8/24/2023 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 8/24/2023 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 9/14/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 9/14/2023 | Approved | JOHN HAYES |
| Green Building Rough | 9/14/2023 | Approved | JOHN HAYES |
| PLUMBING-Rough | 9/14/2023 | Approved | JOHN HAYES |
| Insulation | 9/26/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 9/26/2023 | Partial Approval | JOHN HAYES |
| Shower Pan | 9/26/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 10/16/2023 | Approved | JOHN HAYES |
| Service/Power Release | 2/27/2024 | Not Ready for Inspection | THOMAS FINNILA |
| Service/Power Release | 3/14/2024 | Not Ready for Inspection | JOHN HAYES |
| Sewer | 3/14/2024 | Corrections Issued | JOHN HAYES |
| Sewer | 3/20/2024 | Partial Approval | JOHN HAYES |
| Gas Test | 3/22/2024 | Approved | JOHN HAYES |
| Sewer | 3/22/2024 | Approved | JOHN HAYES |
| Final | 5/1/2024 | Corrections Issued | JOHN HAYES |
| Green Building Final | 5/1/2024 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/1/2024 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 5/1/2024 | Approved | JOHN HAYES |
| Final | 5/16/2024 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 5/16/2024 | SGSOV Approved | JOSE AVILA |
| Final | 5/23/2024 | OK to Issue CofO | JOSE AVILA |
| Service/Power Release | 5/23/2024 | Approved | JOSE AVILA |