19839 W ARCHWOOD ST 91306

Certificate Information: 19839 W ARCHWOOD ST 91306

Application / Permit
21014-20000-02676
Plan Check / Job No.
B21VN06665
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
47'-7" X 13'-11" ADDITION TO THE (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 9/16/2021
Issuing Office
Current Status
CofO Issued on 12/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2021 APPLICANT
Assigned to Plan Check Engineer 5/27/2021 SERGIO MUNIZ
Corrections Issued 5/31/2021 SERGIO MUNIZ
Applicant returned to address corrections 8/31/2021 SERGIO MUNIZ
Building Plans Picked Up 9/3/2021 APPLICANT
Plan Check Approved 9/16/2021 SERGIO MUNIZ
Issued 9/16/2021 APPLICANT
CofO in Progress 11/22/2024 ALEXANDER HANDY
CofO Issued 12/31/2024 JOHN JANSON
Permit Finaled 12/31/2024 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/15/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 6/15/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 8/24/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 8/24/2021 CARLOS AGUILERA

Contact Information

Architect Woodcraft,, Lawrence Albert; Lic. No.: C23651 20812 VENTURA BLVD, STE 205      WOODLAND HILLS, CA 91364
Contractor Owner-Builder       ,

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/22/2021 Partial Inspection STEVEN BACK
Deputy Drilled-In Anchors 10/28/2021 Conditional Approval HENRY KIM
Excavation/Setback/Form/Re-Bar 11/22/2021 Approved STEVEN BACK
Footing/Foundation/Slab 11/22/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 1/28/2022 Partial Approval STEVEN BACK
PLUMBING-Rough 1/28/2022 Partial Approval STEVEN BACK
Insulation 2/11/2022 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 4/13/2022 Not Ready for Inspection JOHNNY MIRANDA
Green Building Rough 4/13/2022 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 4/27/2022 Not Ready for Inspection STEVEN BACK
Green Building Rough 4/27/2022 Not Ready for Inspection STEVEN BACK
Pre-Inspection 5/12/2022 Partial Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Partial Approval STEVEN BACK
Service/Power Release 5/17/2022 Approved STEVEN BACK
BUILDING-Rough-Frame 6/28/2022 Approved STEVEN BACK
ELECTRICAL-Rough 6/28/2022 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Approved STEVEN BACK
Green Building Rough 6/28/2022 Approved STEVEN BACK
HVAC-Rough 6/28/2022 Approved STEVEN BACK
PLUMBING-Rough 6/28/2022 Approved STEVEN BACK
Insulation 7/19/2022 Approved STEVEN BACK
Drywall Nailing 7/27/2022 Approved JESUS PINEDA
ELECTRICAL-Final 11/21/2024 Approved ALEXANDER HANDY
Final 11/21/2024 OK to Issue CofO ALEXANDER HANDY
Green Building Final 11/21/2024 Approved ALEXANDER HANDY
HVAC-Final 11/21/2024 Approved ALEXANDER HANDY
PLUMBING-Final 11/21/2024 Approved ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Approved ALEXANDER HANDY
Smoke Detectors 11/21/2024 Approved ALEXANDER HANDY