5024 N NAGLE AVE 91423

Certificate Information: 5024 N NAGLE AVE 91423

Application / Permit
21014-20000-02657
Plan Check / Job No.
B21VN06615
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY SFD EXCEPT 4 LF AND 2 FT AT SOUTH PORTION OF THE LOT AND BUILD AN IRREGULAR 66'10" X 41' 2 STORY SINGLE FAMILY DWELLING WITH AN ATTACHD TWO CAR GARAGE , NFPA-13D FIRE SPRINKLERS THROUGHOUT, ALL WORK PER ENGINEERING
Permit Issued
Issued on 12/2/2021
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 RARES BODEA
Corrections Issued 6/18/2021 RARES BODEA
Quality Review Completed 6/24/2021 STEVEN KIM
Building Plans Picked Up 6/25/2021 APPLICANT
Applicant returned to address corrections 10/12/2021 RARES BODEA
Applicant returned to address corrections 10/29/2021 RARES BODEA
Plan Check Approved 11/23/2021 RARES BODEA
Plan Check Approved 11/23/2021 RARES BODEA
Issued 12/2/2021 APPLICANT
CofO in Progress 7/6/2022 MISAEL ESPARZA
Permit Finaled 7/23/2022 MICHAEL SMITH
CofO Issued 7/23/2022 MICHAEL SMITH
Permit Finaled 7/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/26/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 7/26/2021 DAGOVERTO GUERRERO
Permit Cleared 7/26/2021 DAGOVERTO GUERRERO
ZI Cleared 7/26/2021 PABLO ESTRADA
Hydrant and Access approval Cleared 9/4/2021 RUEL COLE
Trees in Parkway Cleared 9/22/2021 JOEL HERNANDEZ
Low Impact Development Cleared 9/24/2021 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 9/28/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 9/30/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/10/2021 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 12/13/2021 Corrections Issued MISAEL ESPARZA
Deputy Reinf. Concrete 12/17/2021 Conditional Approval MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 12/17/2021 Approved MISAEL ESPARZA
Footing/Foundation/Slab 12/17/2021 Partial Approval MISAEL ESPARZA
Deputy Reinf. Concrete 12/21/2021 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 12/21/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 12/22/2021 Off-Hour Fees Due
Floor/Roof Diaphrgm/Shear Wall 1/6/2022 Partial Approval MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Corrections Issued MISAEL ESPARZA
Deputy Wood Construction 1/25/2022 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 1/25/2022 Partial Approval MISAEL ESPARZA
HVAC-Rough 2/8/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 2/9/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 2/11/2022 Approved MISAEL ESPARZA
Shower Pan 2/14/2022 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 2/17/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 2/18/2022 Conditional Approval MISAEL ESPARZA
ELECTRICAL-Rough 2/18/2022 Approved MISAEL ESPARZA
Green Building Rough 2/18/2022 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 2/22/2022 Conditional Approval MISAEL ESPARZA
Interior/Exterior Lathing 2/22/2022 Partial Approval MISAEL ESPARZA
HVAC-Rough 2/24/2022 Approved MISAEL ESPARZA
Insulation 2/24/2022 Approved MISAEL ESPARZA
Interior/Exterior Lathing 2/28/2022 Approved MISAEL ESPARZA
Drywall Nailing 3/3/2022 Approved STEPHANIE SWANSON
Final 3/3/2022 Corrections Issued STEPHANIE SWANSON
Green Building Rough 3/3/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 5/13/2022 Corrections Issued MISAEL ESPARZA
HVAC-Final 5/13/2022 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 5/17/2022 Approved MISAEL ESPARZA
PLUMBING-Final 5/18/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/9/2022 Approved MISAEL ESPARZA
Final 6/9/2022 Conditional Approval MISAEL ESPARZA
Footing/Foundation/Slab 6/9/2022 Approved MISAEL ESPARZA
Green Building Final 6/9/2022 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 6/9/2022 SGSOV Approved MISAEL ESPARZA
Smoke Detectors 6/9/2022 Approved MISAEL ESPARZA
Final 6/21/2022 Corrections Issued MATT KELLERMAN
Final 6/29/2022 OK to Issue CofO JACK KARGODORIAN