5845 N SALOMA AVE 91411
Certificate Information: 5845 N SALOMA AVE 91411
- Application / Permit
- 21014-20000-02649
- Plan Check / Job No.
- B21VN06593
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 25' X 39'-10" IRREG SHAPED ADDITION AND REMODEL TO ADD ONE NEW BEDROOM, TWO NEW BATHROOMS, NEW LAUNDRY ROOM, NEW FAMILY ROOM, AND TO ENLARGE/REMODEL KITCHEN. (NFPA-13D FIRE SPRINKLERS REQUIRED)
- Permit Issued
- Issued on 10/13/2021
- Issuing Office
- Current Status
- Issued on 10/13/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/11/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 6/12/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 9/1/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 9/13/2021 | JEROME MAGAT PALMA |
| Plan Check Approved | 9/22/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 9/22/2021 | APPLICANT |
| Issued | 10/13/2021 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2021 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 6/24/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 9/7/2021 | YVAINNE GALSIM |
| Roof/Waste drainage to street | Cleared | 9/8/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basso,, Alexandre; Lic. No.: C77670 | 7231 SUMMITROSE ST TUJUNGA, CA 91042 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/27/2022 | Approved | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 7/21/2022 | Conditional Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 7/21/2022 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 8/5/2022 | Partial Approval | RICHARD DOCKUS |
| Wood Frame | 8/5/2022 | Partial Approval | RICHARD DOCKUS |
| Footing/Foundation/Slab | 8/8/2022 | Partial Approval | ALAN MORELOS |
| Insulation | 8/8/2022 | Partial Approval | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2022 | Corrections Issued | ALAN MORELOS |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2022 | Corrections Issued | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2022 | Approved | RICHARD DOCKUS |
| Footing/Foundation/Slab | 12/13/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/3/2023 | Partial Approval | RYAN SALAZAR |
| HVAC-Rough | 2/13/2023 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 2/23/2023 | Approved | RYAN SALAZAR |
| HVAC-Rough | 2/23/2023 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 2/23/2023 | Approved | RYAN SALAZAR |
| Insulation | 3/3/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/14/2023 | Approved | RYAN SALAZAR |
| Wood Frame | 3/14/2023 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/16/2023 | Partial Approval | RYAN SALAZAR |
| Wood Frame | 3/16/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 3/21/2023 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 3/28/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 3/28/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/6/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 5/8/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Service/Power Release | 5/8/2023 | Not Ready for Inspection | JOHN COLEMAN |
| Service/Power Release | 5/24/2023 | Not Required | RYAN SALAZAR |