7239 N KRAFT AVE 91605

Certificate Information: 7239 N KRAFT AVE 91605

Application / Permit
21014-20000-02642
Plan Check / Job No.
B21VN06567
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
40' X 34'-6" IRREGULAR SHAPED ADDITION OF ACCESSORY DWELLING UNIT PER TO EXISTING DETACHED GARAGE PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/14/2022
Issuing Office
Current Status
CofO Issued on 6/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/25/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 SELLA BENYAMIN
Corrections Issued 7/7/2021 SELLA BENYAMIN
Quality Review Completed 7/14/2021 STEVEN KIM
Building Plans Picked Up 8/19/2021 APPLICANT
Plan Check Approved 1/14/2022 SELLA BENYAMIN
Issued 1/14/2022 APPLICANT
CofO in Progress 6/27/2023 JOHN HAYES
Permit Finaled 6/29/2023 MICHAEL SMITH
CofO Issued 6/29/2023 MICHAEL SMITH
Permit Finaled 6/29/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 7/28/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 7/29/2021 GABRIEL ROBLES
Sewer availability Cleared 7/29/2021 GABRIEL ROBLES
Hydrant and Access approval Cleared 9/15/2021 KURT CORRAL
Low Impact Development Cleared 12/22/2021 TA ANH
Roof/Waste drainage to street Cleared 12/23/2021 DAGOVERTO GUERRERO
Construction near power lines Cleared 1/14/2022 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/29/2022 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 4/15/2022 Partial Approval CALEB MEISTER
Footing/Foundation/Slab 4/15/2022 Approved CALEB MEISTER
Green Building Rough 4/15/2022 Not Ready for Inspection CALEB MEISTER
PLUMBING-Rough 4/15/2022 Partial Approval CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 4/15/2022 SGSOV Not Ready CALEB MEISTER
Sewer 4/15/2022 Not Ready for Inspection CALEB MEISTER
Insulation 4/19/2022 Partial Approval CALEB MEISTER
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Corrections Issued CALEB MEISTER
BUILDING-Rough-Frame 5/12/2022 Not Ready for Inspection JACK KARGODORIAN
Deputy Wood Construction 5/12/2022 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 5/12/2022 Corrections Issued JACK KARGODORIAN
Green Building Rough 5/12/2022 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 5/17/2022 Partial Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Approved JENNIFER RABUCHIN
Green Building Rough 5/17/2022 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 5/17/2022 Corrections Issued JENNIFER RABUCHIN
Wood Frame 5/17/2022 Partial Inspection JENNIFER RABUCHIN
HVAC-Rough 7/11/2022 Approved JOHN HAYES
PLUMBING-Rough 7/11/2022 Approved JOHN HAYES
Shower Pan 7/11/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 7/18/2022 Approved MATT KELLERMAN
ELECTRICAL-Rough 7/18/2022 Conditional Approval MATT KELLERMAN
Green Building Rough 7/18/2022 Approved MATT KELLERMAN
Insulation 7/18/2022 Not Ready for Inspection MATT KELLERMAN
Insulation 7/25/2022 Not Ready for Inspection JOHN HAYES
Insulation 7/28/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 8/3/2022 Partial Approval ALAN MORELOS
Deputy Wood Construction 8/4/2022 Approved ALAN MORELOS
Drywall Nailing 8/11/2022 Approved JOHN HAYES
Shower Pan 8/11/2022 Approved JOHN HAYES
Interior/Exterior Lathing 8/23/2022 Approved JOHN HAYES
Shower Pan 8/23/2022 Approved JOHN HAYES
Final 4/7/2023 Corrections Issued JOHN HAYES
Green Building Final 4/7/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 4/7/2023 SGSOV Not Ready JOHN HAYES
Smoke Detectors 4/7/2023 Approved JOHN HAYES
Final 6/8/2023 Corrections Issued JOHN HAYES
SGSOV-Seismic Gas S/O Valve 6/8/2023 SGSOV Not Ready JOHN HAYES
Final 6/15/2023 Partial Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 6/15/2023 SGSOV Not Ready ROBERT GOLD
Final 6/26/2023 OK to Issue CofO JOHN HAYES
SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Approved JOHN HAYES
Service/Power Release 6/26/2023 Approved JOHN HAYES