11557 W CUMPSTON ST 91601
Certificate Information: 11557 W CUMPSTON ST 91601
- Application / Permit
- 21014-20000-02641
- Plan Check / Job No.
- B21VN06568
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 23' X 18'-6"ADDITION TO AND CONVERT THE (E) TWO CAR DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d).
- Permit Issued
- Issued on 7/22/2021
- Issuing Office
- Current Status
- CofO Issued on 3/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/18/2021 | SERGIO MUNIZ |
| Plan Check Approved | 7/18/2021 | SERGIO MUNIZ |
| Issued | 7/22/2021 | APPLICANT |
| Building Plans Picked Up | 7/23/2021 | APPLICANT |
| CofO in Progress | 12/8/2023 | RYAN SALAZAR |
| Permit Finaled | 3/19/2024 | RUBEN SALAS |
| CofO Issued | 3/19/2024 | RUBEN SALAS |
| Permit Finaled | 3/19/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2021 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 6/25/2021 | ADRIAN CASTRO |
| APC | Cleared | 6/29/2021 | MIGUEL GAMBOA |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2021 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/29/2021 | ADRIAN CASTRO |
Contact Information
| Contractor | Pampa Investment Inc; Lic. No.: 832632-B | 984 BROADWAY #302 CHULA VISTA, CA 91911 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/28/2023 | Partial Inspection | ROBERT GOLD |
| PLUMBING-Rough | 7/6/2023 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 7/11/2023 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 8/21/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 8/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 8/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 8/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 8/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 8/21/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 8/29/2023 | Corrections Issued | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2023 | Partial Approval | JACK KARGODORIAN |
| Green Building Rough | 8/29/2023 | Approved | JACK KARGODORIAN |
| MERV13>=Rough | 8/29/2023 | Approved | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 8/29/2023 | Partial Approval | JACK KARGODORIAN |
| Insulation | 9/8/2023 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/8/2023 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 9/14/2023 | Approved | THOMAS FINNILA |
| Gas Test | 9/14/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 9/14/2023 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 9/14/2023 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 9/14/2023 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/18/2023 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/18/2023 | Approved | CHRISTOPHER ROJAS |
| Gas Test | 9/18/2023 | Approved | CHRISTOPHER ROJAS |
| Insulation | 9/18/2023 | Partial Approval | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/18/2023 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 9/18/2023 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 9/18/2023 | Approved | CHRISTOPHER ROJAS |
| Insulation | 9/20/2023 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 9/22/2023 | Approved | JACK KARGODORIAN |
| Final | 11/1/2023 | Corrections Issued | JOHN COLEMAN |
| Green Building Final | 11/1/2023 | Corrections Issued | JOHN COLEMAN |
| MERV13>=Final | 11/1/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Not Ready | JOHN COLEMAN |
| Smoke Detectors | 11/1/2023 | Approved | JOHN COLEMAN |
| Final | 11/9/2023 | Corrections Issued | JOHN COLEMAN |
| Green Building Final | 11/9/2023 | Corrections Issued | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 11/9/2023 | SGSOV Not Ready | JOHN COLEMAN |
| Final | 11/15/2023 | Corrections Issued | DAVID MATSON |
| Green Building Final | 11/15/2023 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 11/15/2023 | SGSOV Not Ready | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 11/27/2023 | SGSOV Not Ready | JUAN VALENZUELA |
| Final | 11/29/2023 | Not Ready for Inspection | DAVID MATSON |
| Pre-Inspection | 11/29/2023 | Not Ready for Inspection | DAVID MATSON |
| Final | 12/6/2023 | OK to Issue CofO | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/6/2023 | SGSOV Approved | RYAN SALAZAR |