4309 S CAMPBELL DR 90066

Certificate Information: 4309 S CAMPBELL DR 90066

Application / Permit
21014-20000-02636
Plan Check / Job No.
B21VN06539
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL TO EXISTING SINGLE FAMILY DWELLING; ADD 11'-3" X28'-11" AND 34'-3" X 31'-6" TO DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 5/5/2022
Issuing Office
Current Status
CofO Issued on 11/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/26/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 SELLA BENYAMIN
Corrections Issued 6/15/2021 SELLA BENYAMIN
Quality Review Completed 6/16/2021 STEVEN KIM
Building Plans Picked Up 6/18/2021 APPLICANT
Applicant returned to address corrections 4/1/2022 SELLA BENYAMIN
Applicant returned to address corrections 4/22/2022 SELLA BENYAMIN
Plan Check Approved 5/5/2022 SELLA BENYAMIN
Issued 5/5/2022 APPLICANT
CofO in Progress 11/27/2023 JESUS RODRIGUEZ
Permit Finaled 11/29/2023 DANIEL ORRANTE
Permit Finaled 11/29/2023 DANIEL ORRANTE
CofO Issued 11/29/2023 DANIEL ORRANTE

Permit Application Clearance Information

Hydrant and Access approval Cleared 1/10/2022 KURT CORRAL
Eng Process Fee Ord 176,300 Cleared 1/18/2022 DENNIS BRAGIN
Sewer availability Cleared 1/18/2022 DENNIS BRAGIN
Low Impact Development Cleared 3/9/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 3/10/2022 DENNIS BRAGIN

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/20/2022 Approved PATRICK QUALEY
Footing/Foundation/Slab 5/20/2022 Approved PATRICK QUALEY
Deputy Reinf. Concrete 5/26/2022 No Access for Inspection PATRICK QUALEY
Deputy Drilled-In Anchors 6/14/2022 Conditional Approval RICHARD STEINBACH
PLUMBING-Rough 6/15/2022 Partial Approval RICHARD STEINBACH
Wood Frame 6/15/2022 Partial Approval RICHARD STEINBACH
Floor/Roof Diaphrgm/Shear Wall 6/17/2022 Partial Approval STEPHANIE SWANSON
Deputy Wood Construction 9/2/2022 Conditional Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 9/8/2022 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 10/13/2022 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 10/13/2022 Approved JESUS RODRIGUEZ
Green Building Rough 10/13/2022 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 10/13/2022 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 10/13/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 10/13/2022 Approved JESUS RODRIGUEZ
Verify Sprinkler Sign Off 10/13/2022 Approved JESUS RODRIGUEZ
Insulation 10/24/2022 Approved JESUS RODRIGUEZ
Shower Pan 10/24/2022 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/14/2022 Approved JESUS RODRIGUEZ
Drywall Nailing 11/14/2022 Approved JESUS RODRIGUEZ
Green Building Rough 11/14/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 11/14/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 12/8/2022 Approved JESUS RODRIGUEZ
Pre-Inspection 12/8/2022 Partial Inspection JEREMY TODD
ELECTRICAL-Final 11/14/2023 Corrections Issued JESUS RODRIGUEZ
Final 11/14/2023 Corrections Issued JESUS RODRIGUEZ
Green Building Final 11/14/2023 Approved JESUS RODRIGUEZ
HVAC-Final 11/14/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 11/14/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/14/2023 SGSOV Not Ready JESUS RODRIGUEZ
Service/Power Release 11/14/2023 Corrections Issued JESUS RODRIGUEZ
Smoke Detectors 11/14/2023 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 11/27/2023 Approved JESUS RODRIGUEZ
Final 11/27/2023 OK to Issue CofO JESUS RODRIGUEZ
HVAC-Final 11/27/2023 Approved JESUS RODRIGUEZ
PLUMBING-Final 11/27/2023 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Approved JESUS RODRIGUEZ
Service/Power Release 11/27/2023 Approved JESUS RODRIGUEZ