2700 E 2ND ST 90033
Certificate Information: 2700 E 2ND ST 90033
- Application / Permit
- 21014-20000-02616
- Plan Check / Job No.
- B21VN06505
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTIC SPACE INTO TWO BEDROOMS W/STORAGE AND INTERIOR REMODEL THE EXISTING SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 11/1/2021
- Issuing Office
- Current Status
- CofO Issued on 1/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | PETER MOSESIAN |
| Corrections Issued | 6/30/2021 | PETER MOSESIAN |
| Quality Review Completed | 7/13/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/15/2021 | APPLICANT |
| Plan Check Approved | 9/9/2021 | PETER MOSESIAN |
| Issued | 11/1/2021 | APPLICANT |
| CofO in Progress | 1/5/2023 | FREDDIE RIVERA |
| Permit Finaled | 1/14/2023 | DEROLD HAUFF |
| CofO Issued | 1/14/2023 | DEROLD HAUFF |
| Permit Finaled | 1/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/3/2021 | BRIAN MILLER |
| Eng Process Fee Ord 176,300 | Cleared | 8/4/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 8/4/2021 | STEVE MELGAR |
| Tenant Habitability Plan | Cleared | 8/5/2021 | RICARDO BOHORQUEZ |
| Clean Up Green Up | Cleared | 8/6/2021 | LAUREN PADICK |
| ZI | Cleared | 8/6/2021 | LAUREN PADICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Jung,, Jiwon; Lic. No.: C89281 | 2700 E 2ND ST LOS ANGELES, CA 90033 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/4/2021 | Partial Inspection | ROBERT VORHIS |
| Footing/Foundation/Slab | 11/29/2021 | Partial Approval | MASHEL JONGERT |
| METHANE-Barrier | 11/29/2021 | Approved | MASHEL JONGERT |
| METHANE-Subgrade | 11/29/2021 | Approved | MASHEL JONGERT |
| Footing/Foundation/Slab | 12/21/2021 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 1/3/2022 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 3/2/2022 | Corrections Issued | RUBEN SALAS |
| ELECTRICAL-Rough | 3/2/2022 | Off-Hour Fees Due | |
| HVAC-Rough | 3/2/2022 | Corrections Issued | RUBEN SALAS |
| HVAC-Rough | 3/2/2022 | Off-Hour Fees Due | |
| PLUMBING-Rough | 3/2/2022 | Corrections Issued | RUBEN SALAS |
| PLUMBING-Rough | 3/2/2022 | Off-Hour Fees Due | |
| Wood Frame | 3/2/2022 | Corrections Issued | RUBEN SALAS |
| Wood Frame | 3/2/2022 | Off-Hour Fees Due | |
| ELECTRICAL-Rough | 3/8/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 3/8/2022 | Approved | THOMAS LOGRASSO |
| PLUMBING-Rough | 3/8/2022 | Approved | THOMAS LOGRASSO |
| Shower Pan | 3/8/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Wood Frame | 3/10/2022 | Corrections Issued | RUBEN SALAS |
| Green Building Rough | 3/19/2022 | Approved | FREDDIE RIVERA |
| Insulation | 3/19/2022 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 3/19/2022 | Partial Approval | FREDDIE RIVERA |
| Shower Pan | 3/19/2022 | Corrections Issued | FREDDIE RIVERA |
| Wood Frame | 3/19/2022 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 3/24/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 3/24/2022 | Approved | ALIZAH MAYAGOITIA |
| Shower Pan | 3/24/2022 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 3/26/2022 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/14/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 6/14/2022 | Partial Inspection | FREDDIE RIVERA |
| Final | 6/14/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 6/14/2022 | Partial Inspection | FREDDIE RIVERA |
| HVAC-Final | 6/14/2022 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Final | 6/14/2022 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 6/14/2022 | Approved | FREDDIE RIVERA |
| PLUMBING-Final | 6/14/2022 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 6/14/2022 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 6/14/2022 | Partial Inspection | FREDDIE RIVERA |
| Smoke Detectors | 6/14/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Final | 10/18/2022 | Partial Inspection | FREDDIE RIVERA |
| Final | 10/18/2022 | Corrections Issued | FREDDIE RIVERA |
| Green Building Final | 10/18/2022 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 10/18/2022 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 10/18/2022 | Partial Inspection | FREDDIE RIVERA |
| Service/Power Release | 10/18/2022 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Final | 11/2/2022 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Final | 11/2/2022 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 11/2/2022 | No Access for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 11/2/2022 | No Access for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/2/2022 | No Access for Inspection | ALIZAH MAYAGOITIA |
| Service/Power Release | 11/2/2022 | No Access for Inspection | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 11/4/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 11/4/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Green Building Final | 11/4/2022 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 11/4/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/4/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Service/Power Release | 11/4/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 11/18/2022 | Partial Approval | FREDDIE RIVERA |
| Final | 11/28/2022 | Conditional Approval | FREDDIE RIVERA |
| Final | 12/13/2022 | Conditional Approval | FREDDIE RIVERA |
| Final | 1/5/2023 | OK to Issue CofO | FREDDIE RIVERA |