5145 N BELLINGHAM AVE 91607

Certificate Information: 5145 N BELLINGHAM AVE 91607

Application / Permit
21014-20000-02610
Plan Check / Job No.
B21VN06495
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO AND CONVERT (E) DETACHED GARAGE AND 2ND FLOOR REC ROOM TO ACCESSORY DWELLING UNIT (1200 SQ FT) PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 2/9/2022
Issuing Office
Current Status
CofO Issued on 9/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2021 APPLICANT
Assigned to Plan Check Engineer 5/27/2021 JEROME MAGAT PALMA
Corrections Issued 5/29/2021 JEROME MAGAT PALMA
Building Plans Picked Up 6/3/2021 APPLICANT
Applicant returned to address corrections 1/12/2022 JAHANSHAH POURHASSAN
Plan Check Approved 2/9/2022 KAVIAN REFAHI
Issued 2/9/2022 APPLICANT
CofO in Progress 8/23/2022 RAFAEL CORTES
CofO Issued 9/3/2022 MICHAEL SMITH
Permit Finaled 9/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/15/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 6/15/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/16/2021 GABRIEL ROBLES
Sewer availability Cleared 6/16/2021 GABRIEL ROBLES
Specific Plan Cleared 11/9/2021 CORREY KITCHENS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/1/2022 Approved CHRISTOPHE COCHRAN
Deputy Drilled-In Anchors 4/12/2022 Conditional Approval CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 4/18/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 4/18/2022 Corrections Issued CHRISTOPHE COCHRAN
PLUMBING-Rough 4/18/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 4/20/2022 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 4/20/2022 Approved CHRISTOPHE COCHRAN
Underground Mechanical 4/20/2022 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2022 Partial Inspection CHRISTOPHE COCHRAN
ELECTRICAL-Rough 5/12/2022 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Rough 5/12/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 5/12/2022 Corrections Issued CHRISTOPHE COCHRAN
ELECTRICAL-Rough 5/16/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 5/16/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/6/2022 No Access for Inspection CALEB MEISTER
BUILDING-Rough-Frame 6/13/2022 Approved CHRISTOPHE COCHRAN
Green Building Rough 6/13/2022 Approved CHRISTOPHE COCHRAN
Insulation 6/13/2022 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/13/2022 Partial Approval CHRISTOPHE COCHRAN
Shower Pan 6/13/2022 Approved CHRISTOPHE COCHRAN
Drywall Nailing 6/16/2022 Approved RAFAEL CORTES
Interior/Exterior Lathing 6/16/2022 Approved RAFAEL CORTES
Final 7/20/2022 Corrections Issued RAFAEL CORTES
Green Building Final 7/20/2022 Corrections Issued RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 7/20/2022 SGSOV Not Ready RAFAEL CORTES
Smoke Detectors 7/20/2022 Approved RAFAEL CORTES
ELECTRICAL-Final 8/4/2022 Not Ready for Inspection RAFAEL CORTES
Final 8/4/2022 Corrections Issued RAFAEL CORTES
Green Building Final 8/4/2022 Approved RAFAEL CORTES
HVAC-Final 8/4/2022 Corrections Issued RAFAEL CORTES
PLUMBING-Final 8/4/2022 Approved RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 8/4/2022 SGSOV Not Ready RAFAEL CORTES
Final 8/11/2022 Not Ready for Inspection RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Not Ready RAFAEL CORTES
Final 8/23/2022 OK to Issue CofO RAFAEL CORTES
SGSOV-Seismic Gas S/O Valve 8/23/2022 SGSOV Approved RAFAEL CORTES