12811 N PHILLIPPI AVE 91342

Certificate Information: 12811 N PHILLIPPI AVE 91342

Application / Permit
21014-20000-02607
Plan Check / Job No.
B21VN06483
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 15' X 8'2" LAUNDRY (EXT. ACCESS ONLY) AND 9'2" X 8'2" STORAGE (EXT. ACCESS ONLY). CONVERT THE (E) 360 SQ. FT. GARAGE AND ADD 18'2" X 4' INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 8/23/2021
Issuing Office
Valley
Current Status
CofO Issued on 4/12/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2021 APPLICANT
Assigned to Plan Check Engineer 5/27/2021 JEFFREY TANGONAN
Corrections Issued 5/29/2021 JEFFREY TANGONAN
Building Plans Picked Up 6/7/2021 APPLICANT
Issued 8/23/2021 APPLICANT
CofO in Progress 3/17/2023 ARAM AVEDISIAN
CofO Issued 4/12/2023 MICHAEL SMITH
Permit Finaled 4/12/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/2/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/2/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 6/2/2021 ADRIAN CASTRO
Sewer availability Cleared 6/2/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/26/2022 Partial Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 8/2/2022 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 8/8/2022 Approved DEANDRE HOFFMAN
ELECTRICAL-Rough 9/6/2022 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 9/6/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 9/6/2022 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 9/9/2022 Approved ARAM AVEDISIAN
Green Building Rough 9/9/2022 Conditional Approval ARAM AVEDISIAN
PLUMBING-Rough 9/9/2022 Approved ARAM AVEDISIAN
Insulation 9/15/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/15/2022 Partial Approval ARAM AVEDISIAN
Drywall Nailing 9/20/2022 Approved ARAM AVEDISIAN
Green Building Rough 9/20/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 9/22/2022 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 9/22/2022 Not Ready for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 9/26/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 10/21/2022 Approved ARAM AVEDISIAN
Sewer 10/21/2022 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 12/16/2022 No Access for Inspection ARAM AVEDISIAN
Final 12/16/2022 No Access for Inspection ARAM AVEDISIAN
Green Building Final 12/16/2022 No Access for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 12/16/2022 No Access for Inspection ARAM AVEDISIAN
Smoke Detectors 12/16/2022 No Access for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 1/3/2023 Approved ARAM AVEDISIAN
Final 1/3/2023 Corrections Issued ARAM AVEDISIAN
Green Building Final 1/3/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 1/3/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 1/3/2023 Approved ARAM AVEDISIAN
ELECTRICAL-Final 3/17/2023 Approved ARAM AVEDISIAN
Final 3/17/2023 OK to Issue CofO ARAM AVEDISIAN
HVAC-Final 3/17/2023 Approved ARAM AVEDISIAN
PLUMBING-Final 3/17/2023 Approved ARAM AVEDISIAN