14171-14173 W OSBORNE ST 91402

Certificate Information: 14171-14173 W OSBORNE ST 91402

Application / Permit
21014-20000-02584
Plan Check / Job No.
B21VN06414
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
12' X 17' ADDITION AND CONVERSION OF (E) GARAGE TO ADU
Permit Issued
Issued on 1/10/2023
Issuing Office
Current Status
CofO Issued on 8/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 MICHAEL LOPEZ
Corrections Issued 5/26/2021 MICHAEL LOPEZ
Applicant returned to address corrections 9/30/2021 MICHAEL LOPEZ
Applicant returned to address corrections 11/12/2021 MICHAEL LOPEZ
Applicant returned to address corrections 2/8/2022 MICHAEL LOPEZ
Applicant returned to address corrections 12/29/2022 HERNAN ARREOLA
Plan Check Approved 1/9/2023 HERNAN ARREOLA
Issued 1/10/2023 APPLICANT
CofO in Progress 7/25/2024 GREGG CUMMINGS
CofO Issued 8/6/2024 RUBEN SALAS
Permit Finaled 8/6/2024 RUBEN SALAS

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/2/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/2/2021 DAGOVERTO GUERRERO
Construction within easement Cleared 9/20/2021 WALTER RAMIREZ
Address approval Cleared 12/30/2022 LEE GUILBEAUX
Sewer availability Cleared 1/3/2023 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Eden,, Joseph Taki; Lic. No.: NA39955       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/27/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 9/8/2023 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 10/3/2023 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 10/30/2023 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 10/30/2023 Corrections Issued GREGG CUMMINGS
HVAC-Rough 10/30/2023 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 10/30/2023 Approved GREGG CUMMINGS
ELECTRICAL-Rough 11/28/2023 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 11/28/2023 Partial Approval GREGG CUMMINGS
Green Building Rough 11/28/2023 Approved GREGG CUMMINGS
HVAC-Rough 11/28/2023 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 12/4/2023 Approved GREGG CUMMINGS
HVAC-Rough 12/4/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 12/4/2023 Partial Approval GREGG CUMMINGS
Insulation 12/12/2023 Approved GREGG CUMMINGS
Drywall Nailing 12/19/2023 Approved GREGG CUMMINGS
Final 1/24/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 1/24/2024 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/24/2024 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 1/24/2024 Not Ready for Inspection GREGG CUMMINGS
Final 3/14/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 3/14/2024 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 3/14/2024 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 3/14/2024 Not Ready for Inspection GREGG CUMMINGS
Final 4/30/2024 Not Ready for Inspection GREGG CUMMINGS
Smoke Detectors 4/30/2024 Approved GREGG CUMMINGS
Final 7/24/2024 OK to Issue CofO GREGG CUMMINGS
Service/Power Release 7/24/2024 Approved GREGG CUMMINGS