14171-14173 W OSBORNE ST 91402
Certificate Information: 14171-14173 W OSBORNE ST 91402
- Application / Permit
- 21014-20000-02584
- Plan Check / Job No.
- B21VN06414
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 12' X 17' ADDITION AND CONVERSION OF (E) GARAGE TO ADU
- Permit Issued
- Issued on 1/10/2023
- Issuing Office
- Current Status
- CofO Issued on 8/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | MICHAEL LOPEZ |
| Corrections Issued | 5/26/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 9/30/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 11/12/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/8/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 12/29/2022 | HERNAN ARREOLA |
| Plan Check Approved | 1/9/2023 | HERNAN ARREOLA |
| Issued | 1/10/2023 | APPLICANT |
| CofO in Progress | 7/25/2024 | GREGG CUMMINGS |
| CofO Issued | 8/6/2024 | RUBEN SALAS |
| Permit Finaled | 8/6/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/2/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/2/2021 | DAGOVERTO GUERRERO |
| Construction within easement | Cleared | 9/20/2021 | WALTER RAMIREZ |
| Address approval | Cleared | 12/30/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/3/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Eden,, Joseph Taki; Lic. No.: NA39955 | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/27/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 9/8/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2023 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/30/2023 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/30/2023 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 10/30/2023 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 10/30/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/28/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2023 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 11/28/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 11/28/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/4/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 12/4/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 12/4/2023 | Partial Approval | GREGG CUMMINGS |
| Insulation | 12/12/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 12/19/2023 | Approved | GREGG CUMMINGS |
| Final | 1/24/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/24/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/24/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 1/24/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 3/14/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 3/14/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 3/14/2024 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 3/14/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 4/30/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 4/30/2024 | Approved | GREGG CUMMINGS |
| Final | 7/24/2024 | OK to Issue CofO | GREGG CUMMINGS |
| Service/Power Release | 7/24/2024 | Approved | GREGG CUMMINGS |