7732 N CHIMINEAS AVE 91335
Certificate Information: 7732 N CHIMINEAS AVE 91335
- Application / Permit
- 21014-20000-02567
- Plan Check / Job No.
- B21VN06365
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF A BEDROOM, BATHROOM, CLOSET, AND A DECK WITH A PATIO COVER.
- Permit Issued
- Issued on 10/9/2021
- Issuing Office
- Current Status
- CofO Issued on 3/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2021 | LUIS RINCON |
| Corrections Issued | 5/24/2021 | LUIS RINCON |
| Applicant returned to address corrections | 8/24/2021 | LUIS RINCON |
| Plan Check Approved | 8/25/2021 | LUIS RINCON |
| Building Plans Picked Up | 10/6/2021 | APPLICANT |
| Issued | 10/9/2021 | APPLICANT |
| CofO in Progress | 1/27/2022 | VINCENT HANLEY |
| CofO Issued | 3/6/2022 | MICHAEL SMITH |
| Permit Finaled | 3/6/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/28/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/28/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/29/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gosen,, James W; Lic. No.: C43590 | 15315 BLEDSOE ST SYLMAR, CA 91342 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/12/2021 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 11/12/2021 | Approved | VINCENT HANLEY |
| Pre-Inspection | 11/12/2021 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/3/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Wood Frame | 12/3/2021 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/8/2021 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2021 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 12/8/2021 | Corrections Issued | VINCENT HANLEY |
| Wood Frame | 12/8/2021 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/15/2021 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 12/15/2021 | Approved | VINCENT HANLEY |
| Green Building Rough | 12/15/2021 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 12/15/2021 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 12/22/2021 | Not Ready for Inspection | VINCENT HANLEY |
| Green Building Rough | 12/22/2021 | Approved | VINCENT HANLEY |
| HVAC-Rough | 12/22/2021 | Approved | VINCENT HANLEY |
| Insulation | 12/22/2021 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 12/22/2021 | Approved | VINCENT HANLEY |
| Drywall Nailing | 12/28/2021 | Approved | JESUS PINEDA |
| Green Building Rough | 12/28/2021 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 1/26/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 1/26/2022 | Approved | VINCENT HANLEY |
| Final | 1/26/2022 | OK to Issue CofO | VINCENT HANLEY |
| Green Building Final | 1/26/2022 | Approved | VINCENT HANLEY |
| HVAC-Final | 1/26/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 1/26/2022 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 1/26/2022 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 1/26/2022 | Approved | VINCENT HANLEY |