15708 W MINNEHAHA ST 91344

Certificate Information: 15708 W MINNEHAHA ST 91344

Application / Permit
21014-20000-02551
Plan Check / Job No.
B21VN06333
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 6'-5" x 23'-7" , 8'-9" x 8'-5" AND 21'-5" x 10'-0" ADDITION TO THE (E) SINGLE FAMILY DWELLING FOR A NEW BEDROOM, NEW LAUNDRY ROOM AND EXTEND TWO (E)BEDROOMS. INTERIOR REMODEL TO RELOCATE KITCHEN AND DINING ROOM. REMODEL TWO (E)BATHROOMS.
Permit Issued
Issued on 7/8/2021
Issuing Office
Current Status
Issued on 7/8/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/20/2021 APPLICANT
Assigned to Plan Check Engineer 5/27/2021 SARKIS HARABEDIAN
Corrections Issued 5/29/2021 SARKIS HARABEDIAN
Building Plans Picked Up 6/3/2021 APPLICANT
Plan Check Approved 7/6/2021 SERGIO MUNIZ
Issued 7/8/2021 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/21/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/22/2021 GABRIEL ROBLES
Sewer availability Cleared 6/22/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/9/2021 Approved MARK JOHNSON
Excavation/Setback/Form/Re-Bar 9/14/2021 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 9/14/2021 Not Ready for Inspection MARK JOHNSON
Excavation/Setback/Form/Re-Bar 9/21/2021 Approved MARK JOHNSON
Footing/Foundation/Slab 9/21/2021 Approved MARK JOHNSON
Sewer 9/21/2021 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 11/12/2021 Partial Approval JENNIFER RABUCHIN
Deputy Wood Construction 12/1/2021 Conditional Approval MICHAEL TEMPLE
ELECTRICAL-Rough 12/9/2021 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 12/9/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 12/15/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 12/15/2021 Partial Approval CHRISTOPHER DELLEFIELD
Green Building Rough 12/15/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
MERV13>=Rough 12/15/2021 Approved CHRISTOPHER DELLEFIELD
Insulation 12/21/2021 No Access for Inspection CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 12/23/2021 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 12/23/2021 Partial Approval JENNIFER RABUCHIN
Insulation 12/23/2021 Partial Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 12/23/2021 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 12/30/2021 Partial Approval JOHN HAYES
Green Building Rough 12/30/2021 Partial Approval JOHN HAYES
Interior/Exterior Lathing 12/30/2021 Partial Approval JOHN HAYES
Deputy Wood Construction 1/21/2022 Partial Approval MICHAEL TEMPLE
BUILDING-Rough-Frame 1/26/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 1/26/2022 Partial Approval JENNIFER RABUCHIN
Gas Test 1/26/2022 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 1/26/2022 Not Ready for Inspection JENNIFER RABUCHIN
Insulation 1/26/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 2/2/2022 Approved JESUS RODRIGUEZ
Green Building Rough 2/2/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/2/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 2/3/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 3/23/2022 No Access for Inspection JAVIER RAMOS JR
Interior/Exterior Lathing 3/23/2022 No Access for Inspection JAVIER RAMOS JR
Final 7/16/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 7/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
MERV13>=Final 7/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Not Ready CHRISTOPHER ROJAS
Smoke Detectors 7/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS