17141 W CLEMONS DR 91436

Certificate Information: 17141 W CLEMONS DR 91436

Application / Permit
21014-20000-02542
Plan Check / Job No.
B21VN06318
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 1ST FLOOR ADDITION W/ NEW COVERED PATIO (16'-6"x 15'6") 256 SQFT AND 2ND FLOOR ADDITION (16'-6"x27'-6") 410 SQFT & INTERIOR REMODEL OF EXISTING 2-STORY SFD W/NFPA-13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 9/9/2021
Issuing Office
Current Status
CofO Issued on 1/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/24/2021 APPLICANT
Assigned to Plan Check Engineer 6/24/2021 PETER MOSESIAN
Corrections Issued 6/29/2021 PETER MOSESIAN
Quality Review Completed 7/14/2021 OMID HEDAYAT
Building Plans Picked Up 7/16/2021 APPLICANT
Plan Check Approved 9/9/2021 PETER MOSESIAN
Issued 9/9/2021 APPLICANT
CofO in Progress 1/12/2024 VINCENT HANLEY
Permit Finaled 1/18/2024 JOHN JANSON
CofO Issued 1/18/2024 JOHN JANSON
Permit Finaled 1/18/2024 JOHN JANSON

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/26/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 7/26/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 7/26/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 7/26/2021 CARLOS AGUILERA
BHO/Hillside ordinance Cleared 7/26/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/28/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/28/2021 CARLOS AGUILERA
Specific Plan Cleared 8/6/2021 OLGA AYALA
ZI Cleared 8/6/2021 OLGA AYALA
Grading Pre-Inspection Cleared 9/9/2021 PETER MOSESIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Sadeghi,, Hamid M; Lic. No.: C33504 30941 W AGOURA RD 236      WESTLAKE VILLAGE, CA 91361

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/3/2021 Approved RONALD COWAN
Footing/Foundation/Slab 11/9/2021 Approved RONALD COWAN
Deputy Reinf. Concrete 11/15/2021 Conditional Approval MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 1/28/2022 Partial Approval MICHAEL TEMPLE
Floor/Roof Diaphrgm/Shear Wall 2/15/2022 Not Ready for Inspection PETER FOLLING
Floor/Roof Diaphrgm/Shear Wall 2/22/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 3/17/2022 Corrections Issued DAVID SANDOVAL
PLUMBING-Rough 3/23/2022 Partial Approval PETER FOLLING
ELECTRICAL-Rough 4/5/2022 Approved VINCENT HANLEY
Service/Power Release 4/5/2022 Approved VINCENT HANLEY
PLUMBING-Rough 4/8/2022 Approved VINCENT HANLEY
HVAC-Rough 4/15/2022 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 4/25/2022 Approved VINCENT HANLEY
ELECTRICAL-Rough 4/25/2022 Approved VINCENT HANLEY
Green Building Rough 4/25/2022 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 4/25/2022 Approved VINCENT HANLEY
Insulation 4/29/2022 Approved MORRIS JACKSON
Drywall Nailing 5/2/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 6/15/2022 Partial Approval MORRIS JACKSON
Shower Pan 6/15/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 8/5/2022 Approved VINCENT HANLEY
ELECTRICAL-Final 2/27/2023 Corrections Issued VINCENT HANLEY
Final 2/27/2023 Corrections Issued VINCENT HANLEY
Green Building Final 2/27/2023 Approved VINCENT HANLEY
HVAC-Final 2/27/2023 Approved VINCENT HANLEY
PLUMBING-Final 2/27/2023 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 2/27/2023 SGSOV Approved VINCENT HANLEY
Smoke Detectors 2/27/2023 Approved VINCENT HANLEY
Final 3/6/2023 Corrections Issued VINCENT HANLEY
Special/Order Compliance 3/6/2023 Partial Inspection JUSTIN HAWLEY
Final 1/5/2024 Corrections Issued VINCENT HANLEY
Final 1/12/2024 OK to Issue CofO VINCENT HANLEY