16443-16445 W BRYANT ST 91343

Certificate Information: 16443-16445 W BRYANT ST 91343

Application / Permit
21014-20000-02525
Plan Check / Job No.
B21VN06271
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) 21' X 26' ATTACHED GARAGE AND ADD 5'-6" X 21' & 5'-3" X 6'-6" TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/19/2021
Issuing Office
Current Status
CofO Issued on 2/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/19/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 RAPHAEL ROSAS
Corrections Issued 5/29/2021 RAPHAEL ROSAS
Applicant returned to address corrections 10/26/2021 RAPHAEL ROSAS
Building Plans Picked Up 11/3/2021 APPLICANT
Issued 11/19/2021 APPLICANT
CofO in Progress 1/27/2023 RAUL OLAGI
CofO Issued 2/7/2023 MICHAEL SMITH
Permit Finaled 2/7/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/23/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/23/2021 CARLOS AGUILERA
Sewer availability Cleared 9/23/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/2/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/6/2021 Conditional Approval RAUL OLAGI
PLUMBING-Rough 12/15/2021 Partial Approval RAUL OLAGI
Sewer 12/15/2021 Partial Approval RAUL OLAGI
Footing/Foundation/Slab 12/22/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 1/3/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/3/2022 Corrections Issued RAUL OLAGI
Green Building Rough 1/3/2022 Not Ready for Inspection RAUL OLAGI
PLUMBING-Rough 1/3/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 3/9/2022 Not Ready for Inspection RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/9/2022 Partial Approval RAUL OLAGI
Green Building Rough 3/9/2022 Not Ready for Inspection RAUL OLAGI
BUILDING-Rough-Frame 4/20/2022 Corrections Issued RAUL OLAGI
ELECTRICAL-Rough 4/20/2022 Corrections Issued RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/20/2022 Approved RAUL OLAGI
HVAC-Rough 4/20/2022 Corrections Issued RAUL OLAGI
PLUMBING-Rough 4/20/2022 Corrections Issued RAUL OLAGI
BUILDING-Rough-Frame 4/25/2022 Approved RAUL OLAGI
ELECTRICAL-Rough 4/25/2022 Approved RAUL OLAGI
Green Building Rough 4/25/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 4/25/2022 Partial Approval RAUL OLAGI
PLUMBING-Rough 4/25/2022 Approved RAUL OLAGI
Insulation 4/28/2022 Approved DEANDRE HOFFMAN
Drywall Nailing 5/3/2022 Partial Approval DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Approved DEANDRE HOFFMAN
Drywall Nailing 5/6/2022 Approved RAUL OLAGI
Sewer 5/6/2022 Approved RAUL OLAGI
Shower Pan 5/11/2022 Not Ready for Inspection ALAN MORELOS
Shower Pan 5/16/2022 Approved RAUL OLAGI
Interior/Exterior Lathing 5/20/2022 Approved RAUL OLAGI
ELECTRICAL-Final 8/11/2022 Approved ALAN MORELOS
Final 8/11/2022 Corrections Issued ALAN MORELOS
Green Building Final 8/11/2022 Not Ready for Inspection ALAN MORELOS
HVAC-Final 8/11/2022 Corrections Issued ALAN MORELOS
PLUMBING-Final 8/11/2022 Approved ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 8/11/2022 SGSOV Approved ALAN MORELOS
Smoke Detectors 8/11/2022 Approved ALAN MORELOS
Final 11/17/2022 Corrections Issued MICHEL ABAJAN
Green Building Final 11/17/2022 Approved MICHEL ABAJAN
HVAC-Final 11/17/2022 Approved MICHEL ABAJAN
Final 1/27/2023 OK to Issue CofO RAUL OLAGI