1709 S DURANGO AVE 90035
Certificate Information: 1709 S DURANGO AVE 90035
- Application / Permit
- 21014-20000-02512
- Plan Check / Job No.
- B21VN06228
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- DEMO MOST OF INT. AND EXT. WALLS OF (E) RESIDENCE AND ERECT IRR. SHAPED 61'-0" x 36'-9" TWO-STORY SINGLE FAMILY DWELLING W/ ATT. 2-CAR GARAGE AND ATT. OPEN TRELLIS; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED
- Permit Issued
- Issued on 9/27/2021
- Issuing Office
- Current Status
- CofO Issued on 3/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | SEAN SHAHMIRI |
| Corrections Issued | 6/5/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 6/7/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/18/2021 | APPLICANT |
| Applicant returned to address corrections | 8/2/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 8/26/2021 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 9/15/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 9/27/2021 | SEAN SHAHMIRI |
| Issued | 9/27/2021 | APPLICANT |
| CofO in Progress | 3/13/2023 | JEREMY TODD |
| Permit Finaled | 3/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/15/2023 | DANIEL ORRANTE |
| CofO Issued | 3/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2021 | THOMAS LANG |
| Sewer availability | Cleared | 6/24/2021 | THOMAS LANG |
| Trees in Parkway | Cleared | 7/29/2021 | JOHN KIM |
| Permit | Cleared | 9/9/2021 | THOMAS LANG |
| Low Impact Development | Cleared | 9/13/2021 | SARAH YOUSSEF |
| Grading Pre-Inspection | Cleared | 9/15/2021 | SEAN SHAHMIRI |
| Roof/Waste drainage to street | Cleared | 9/17/2021 | THAN WIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/4/2021 | Corrections Issued | EVAN COOPER |
| METHANE-Barrier | 11/4/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Subgrade | 11/4/2021 | Not Ready for Inspection | EVAN COOPER |
| Sewer | 11/4/2021 | Not Ready for Inspection | EVAN COOPER |
| Underground Mechanical | 11/4/2021 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Rough | 12/28/2021 | Partial Approval | EVAN COOPER |
| Footing/Foundation/Slab | 1/18/2022 | Partial Approval | JOHNNY MIRANDA |
| METHANE-Barrier | 1/18/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| METHANE-Subgrade | 1/18/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 1/26/2022 | Approved | EVAN COOPER |
| METHANE-Barrier | 1/26/2022 | Approved | EVAN COOPER |
| METHANE-Subgrade | 1/26/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2022 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2022 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 3/30/2022 | Partial Inspection | KEVIN SARGSYAN |
| HVAC-Rough | 4/6/2022 | Corrections Issued | EVAN COOPER |
| METHANE-Rough | 4/6/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 4/6/2022 | Approved | EVAN COOPER |
| Shower Pan | 4/6/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 5/2/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 5/2/2022 | Approved | EVAN COOPER |
| Shower Pan | 5/2/2022 | Approved | EVAN COOPER |
| Deputy Wood Construction | 5/9/2022 | Conditional Approval | EVAN COOPER |
| BUILDING-Rough-Frame | 5/17/2022 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2022 | Approved | EVAN COOPER |
| Green Building Rough | 5/17/2022 | Not Ready for Inspection | EVAN COOPER |
| Interior/Exterior Lathing | 5/17/2022 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 5/23/2022 | Approved | EVAN COOPER |
| Insulation | 7/1/2022 | Corrections Issued | EVAN COOPER |
| Drywall Nailing | 7/8/2022 | Approved | EVAN COOPER |
| Green Building Rough | 7/8/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 12/29/2022 | Approved | JEREMY TODD |
| Gas Test | 12/29/2022 | Approved | JEREMY TODD |
| HVAC-Final | 12/29/2022 | Approved | JEREMY TODD |
| PLUMBING-Final | 12/29/2022 | Approved | JEREMY TODD |
| Service/Power Release | 12/29/2022 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 3/1/2023 | Approved | JEREMY TODD |
| Final | 3/1/2023 | Corrections Issued | JEREMY TODD |
| Green Building Final | 3/1/2023 | Approved | JEREMY TODD |
| SGSOV-Seismic Gas S/O Valve | 3/1/2023 | SGSOV Approved | JEREMY TODD |
| Smoke Detectors | 3/1/2023 | Approved | JEREMY TODD |
| Final | 3/10/2023 | OK to Issue CofO | JEREMY TODD |