11060 W LEMAY ST 91606
Certificate Information: 11060 W LEMAY ST 91606
- Application / Permit
- 21014-20000-02506
- Plan Check / Job No.
- B21VN06220
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE (E) PATIO, 20'-2" X 32'-0" IRREGULAR SHAPED ADDITION TO THE (E) SFD. FIRE SPRINKLER REQUIRED THROUGHOUT.
- Permit Issued
- Issued on 6/22/2021
- Issuing Office
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 5/29/2021 | ARTIN ZARUKIAN |
| Plan Check Approved | 6/4/2021 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 6/4/2021 | APPLICANT |
| Issued | 6/22/2021 | APPLICANT |
| CofO in Progress | 3/16/2022 | MISAEL ESPARZA |
| Permit Finaled | 4/19/2022 | MICHAEL SMITH |
| CofO Issued | 4/19/2022 | MICHAEL SMITH |
| Permit Finaled | 4/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 6/3/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/24/2021 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 8/25/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 9/10/2021 | Partial Approval | DANIEL DREW |
| PLUMBING-Rough | 9/10/2021 | Partial Approval | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2021 | Partial Approval | DANIEL DREW |
| Insulation | 9/14/2021 | Partial Approval | DANIEL DREW |
| Drywall Nailing | 10/6/2021 | Not Ready for Inspection | DANIEL DREW |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 10/26/2021 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 10/26/2021 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Rough | 10/26/2021 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 10/26/2021 | Corrections Issued | CALEB MEISTER |
| BUILDING-Rough-Frame | 11/1/2021 | Approved | DANIEL DREW |
| Green Building Rough | 11/1/2021 | Approved | DANIEL DREW |
| HVAC-Rough | 11/1/2021 | Approved | DANIEL DREW |
| PLUMBING-Rough | 11/1/2021 | Approved | DANIEL DREW |
| Insulation | 11/4/2021 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 11/9/2021 | Approved | CALEB MEISTER |
| ELECTRICAL-Rough | 11/9/2021 | Approved | CALEB MEISTER |
| Verify Sprinkler Sign Off | 11/9/2021 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 11/19/2021 | Approved | CALEB MEISTER |
| Final | 1/18/2022 | Corrections Issued | DAVID MATSON |
| Green Building Final | 1/18/2022 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 1/18/2022 | SGSOV Not Ready | DAVID MATSON |
| Smoke Detectors | 1/18/2022 | Approved | DAVID MATSON |
| Final | 1/24/2022 | Partial Approval | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 1/24/2022 | SGSOV Approved | DAVID MATSON |
| Final | 3/15/2022 | OK to Issue CofO | MISAEL ESPARZA |