7901 S GLIDER AVE 90045
Certificate Information: 7901 S GLIDER AVE 90045
- Application / Permit
- 21014-20000-02494
- Plan Check / Job No.
- B21VN06179
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT ATTACHED GARAGE INTO BEDROOM (18'-3"x20'-7"), ADD NEW CARPORT (8'-6"x34'-0") TO REAR OF SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 12/8/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/10/2021 | PETER MOSESIAN |
| Corrections Issued | 6/12/2021 | PETER MOSESIAN |
| Quality Review Completed | 6/17/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 8/6/2021 | PETER MOSESIAN |
| Plan Check Approved | 11/12/2021 | PETER MOSESIAN |
| Issued | 12/8/2021 | APPLICANT |
| CofO in Progress | 10/5/2022 | BOBBY KEY |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
| CofO Issued | 10/6/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/6/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2021 | SAUL GARCIA |
| Permit | Cleared | 7/8/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 7/8/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2021 | SAUL GARCIA |
| Specific Plan | Cleared | 9/8/2021 | VALERIA CEJA |
| Roof/Waste drainage to street | Cleared | 9/22/2021 | RAYMOND MUGAMBWA |
| Trees in Parkway | Cleared | 10/21/2021 | ADALBERTO VERA |
Contact Information
| Contractor | Sherman Oaks Construction Inc; Lic. No.: 859762-B | 7800 BOTHWELL ROAD RESEDA, CA 91335 |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/19/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 1/19/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 2/16/2022 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 2/16/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 2/28/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/28/2022 | Partial Approval | RYAN SALAZAR |
| Footing/Foundation/Slab | 3/17/2022 | Approved | BOBBY KEY |
| Shower Pan | 3/17/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 3/25/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 4/1/2022 | Corrections Issued | BOBBY KEY |
| Insulation | 4/1/2022 | Not Ready for Inspection | BOBBY KEY |
| PLUMBING-Rough | 4/1/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 4/14/2022 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 4/14/2022 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 4/14/2022 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 6/8/2022 | Approved | BOBBY KEY |
| Green Building Rough | 6/8/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 6/8/2022 | Approved | BOBBY KEY |
| Insulation | 6/8/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 6/15/2022 | Approved | BOBBY KEY |
| Final | 6/15/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 9/16/2022 | Approved | BOBBY KEY |
| Final | 9/16/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 9/16/2022 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 9/16/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 9/16/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 9/16/2022 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 9/16/2022 | Corrections Issued | BOBBY KEY |
| Final | 10/4/2022 | OK to Issue CofO | BOBBY KEY |
| Green Building Final | 10/4/2022 | Approved | BOBBY KEY |
| HVAC-Final | 10/4/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/4/2022 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 10/4/2022 | Approved | BOBBY KEY |