17750 W VANOWEN ST 91335
Certificate Information: 17750 W VANOWEN ST 91335
- Application / Permit
- 21014-20000-02493
- Plan Check / Job No.
- B21VN06177
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 9'-9" X 15'-6" FOR NEW STUDY ROOM, REMODEL (E) BEDROOM, (N) FULL BATHROOM, REMODEL (E) KITCHEN. ALL WORK PER WFPP.
- Permit Issued
- Issued on 6/3/2021
- Issuing Office
- Current Status
- CofO Issued on 10/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2021 | JENNIFER LEE |
| Corrections Issued | 5/25/2021 | JENNIFER LEE |
| Plan Check Approved | 6/3/2021 | JENNIFER LEE |
| Issued | 6/3/2021 | APPLICANT |
| Building Plans Picked Up | 6/4/2021 | APPLICANT |
| CofO in Progress | 10/4/2023 | JEFFREY BULL |
| Permit Finaled | 10/6/2023 | JOHN JANSON |
| CofO Issued | 10/6/2023 | JOHN JANSON |
| Permit Finaled | 10/6/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/25/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/25/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Partial Approval | JEFFREY BULL |
| BUILDING-Rough-Frame | 6/23/2023 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 6/23/2023 | Approved | JEFFREY BULL |
| Green Building Rough | 6/23/2023 | Approved | JEFFREY BULL |
| HVAC-Rough | 6/23/2023 | Approved | JEFFREY BULL |
| PLUMBING-Rough | 6/23/2023 | Approved | JEFFREY BULL |
| Insulation | 6/26/2023 | Approved | JEFFREY BULL |
| Drywall Nailing | 7/5/2023 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 7/5/2023 | Approved | HENRY KIM |
| Shower Pan | 7/5/2023 | Not Ready for Inspection | HENRY KIM |
| ELECTRICAL-Final | 9/27/2023 | Approved | JEFFREY BULL |
| Final | 9/27/2023 | OK to Issue CofO | JEFFREY BULL |
| Footing/Foundation/Slab | 9/27/2023 | Approved | JEFFREY BULL |
| Green Building Final | 9/27/2023 | Approved | JEFFREY BULL |
| HVAC-Final | 9/27/2023 | Approved | JEFFREY BULL |
| PLUMBING-Final | 9/27/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 9/27/2023 | SGSOV Approved | JEFFREY BULL |
| Smoke Detectors | 9/27/2023 | Approved | JEFFREY BULL |