8144 S COLEGIO DR 90045

Certificate Information: 8144 S COLEGIO DR 90045

Application / Permit
21014-20000-02492
Plan Check / Job No.
B21VN06174
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 32'-11" X 37'-6" IRREGULAR SHAPED AND MAJOR REMODEL TO (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/27/2022
Issuing Office
Current Status
CofO Issued on 11/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 RAPHAEL ROSAS
Corrections Issued 5/30/2021 RAPHAEL ROSAS
Applicant returned to address corrections 11/29/2021 RAPHAEL ROSAS
Plan Check Approved 3/3/2022 RAPHAEL ROSAS
Building Plans Picked Up 3/4/2022 APPLICANT
Issued 7/27/2022 APPLICANT
CofO in Progress 11/14/2023 BOBBY KEY
Permit Finaled 11/14/2023 DANIEL ORRANTE
CofO Issued 11/14/2023 DANIEL ORRANTE
Permit Finaled 11/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 9/7/2021 TA ANH
Roof/Waste drainage to street Cleared 9/22/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/24/2021 DINAH GARIN
Sewer availability Cleared 9/24/2021 DINAH GARIN
Grading Pre-Inspection Cleared 12/28/2021 SERGIO VALENZUELA
GPI Written Notices Cleared 3/3/2022 RAPHAEL ROSAS

Contact Information

Contractor Owner-Builder       ,
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/28/2022 Approved BOBBY KEY
Footing/Foundation/Slab 10/28/2022 Approved BOBBY KEY
METHANE-Barrier 10/28/2022 Approved BOBBY KEY
METHANE-Subgrade 10/28/2022 Approved BOBBY KEY
Wood Frame 11/10/2022 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 11/15/2022 Partial Approval BOBBY KEY
Deputy Wood Construction 1/23/2023 Conditional Approval BOBBY KEY
ELECTRICAL-Rough 2/14/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Approved BOBBY KEY
HVAC-Rough 2/14/2023 Approved BOBBY KEY
PLUMBING-Rough 2/14/2023 Approved BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 2/28/2023 Partial Approval EVAN COOPER
Underground Mechanical 2/28/2023 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 3/13/2023 Approved BOBBY KEY
Green Building Rough 3/13/2023 Approved BOBBY KEY
Insulation 3/13/2023 Approved BOBBY KEY
Interior/Exterior Lathing 3/13/2023 Approved BOBBY KEY
Drywall Nailing 3/20/2023 Approved BOBBY KEY
Gas Test 5/12/2023 Approved BOBBY KEY
ELECTRICAL-Final 10/11/2023 Approved BOBBY KEY
Final 10/11/2023 Corrections Issued BOBBY KEY
Green Building Final 10/11/2023 Approved BOBBY KEY
HVAC-Final 10/11/2023 Approved BOBBY KEY
PLUMBING-Final 10/11/2023 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 10/11/2023 SGSOV Approved BOBBY KEY
Service/Power Release 10/11/2023 Approved BOBBY KEY
Smoke Detectors 10/11/2023 Approved BOBBY KEY
Final 11/14/2023 OK to Issue CofO BOBBY KEY