137 1/2 W 84TH ST 90003

Certificate Information: 137 1/2 W 84TH ST 90003

Application / Permit
21014-20000-02487
Plan Check / Job No.
B21VN06146
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 14'-7" X 19' IRREGULAR SHAPED GARAGE AND ADD 10' X 12'-2" FOR (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 3/14/2022
Issuing Office
Current Status
Issued on 3/14/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/20/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 RAPHAEL ROSAS
Corrections Issued 5/29/2021 RAPHAEL ROSAS
Applicant returned to address corrections 2/22/2022 RAPHAEL ROSAS
Issued 3/14/2022 APPLICANT
Building Plans Picked Up 3/18/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/4/2021 RENZ SORIANO
Address approval Cleared 10/22/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/26/2021 STEVE MELGAR
Sewer availability Cleared 10/26/2021 STEVE MELGAR
Tenant Habitability Plan Cleared 11/1/2021 RICARDO BOHORQUEZ
Construction near power lines Cleared 1/28/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/4/2022 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 4/5/2022 Conditional Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/7/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 4/26/2022 Corrections Issued LILIANA PORTILLO
HVAC-Rough 4/26/2022 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 4/26/2022 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 5/4/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 5/4/2022 Approved LILIANA PORTILLO
HVAC-Rough 5/4/2022 Conditional Approval LILIANA PORTILLO
PLUMBING-Rough 5/4/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 5/9/2022 Conditional Approval LILIANA PORTILLO
BUILDING-Rough-Frame 5/12/2022 Approved LILIANA PORTILLO
Green Building Rough 5/12/2022 Approved LILIANA PORTILLO
Insulation 5/12/2022 Approved LILIANA PORTILLO
Interior/Exterior Lathing 5/12/2022 Partial Approval LILIANA PORTILLO
Underground Mechanical 5/12/2022 Approved LILIANA PORTILLO
Drywall Nailing 5/18/2022 Approved LILIANA PORTILLO
Green Building Final 9/2/2022 Not Ready for Inspection LILIANA PORTILLO
Pre-Inspection 9/2/2022 Not Ready for Inspection LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 9/2/2022 SGSOV Not Ready LILIANA PORTILLO
Smoke Detectors 9/2/2022 Corrections Issued LILIANA PORTILLO