11331-11333 W SATICOY ST 91352

Certificate Information: 11331-11333 W SATICOY ST 91352

Application / Permit
21014-20000-02486
Plan Check / Job No.
B21VN06142
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert existing attached garage into ADU with addition,new ATTACHED ADU PER ORDINANCE
Permit Issued
Issued on 7/22/2021
Issuing Office
Current Status
CofO Issued on 3/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2021 APPLICANT
Assigned to Plan Check Engineer 5/18/2021 RARES BODEA
Corrections Issued 5/24/2021 CARLOS MONTES
Applicant returned to address corrections 6/3/2021 CARLOS MONTES
Applicant returned to address corrections 6/14/2021 JOE VO
Plan Check Approved 6/24/2021 JOE VO
Issued 7/22/2021 APPLICANT
CofO in Progress 2/6/2023 JOHN COLEMAN
CofO Issued 3/2/2023 MICHAEL SMITH
Permit Finaled 3/2/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/25/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 6/1/2021 GABRIEL ROBLES
Sewer availability Cleared 6/1/2021 GABRIEL ROBLES
Clean Up Green Up Cleared 6/10/2021 TERRI OSBORNE
ZA Case Cleared 6/10/2021 TERRI OSBORNE
ZA Case Cleared 6/10/2021 TERRI OSBORNE
Roof/Waste drainage to street Cleared 6/15/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM WREN, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/16/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Pre-Inspection 9/16/2021 Approved CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 11/22/2021 No Access for Inspection WILLIAM KUEHN
Excavation/Setback/Form/Re-Bar 11/23/2021 Corrections Issued DAVID MATSON
Footing/Foundation/Slab 11/23/2021 Not Ready for Inspection DAVID MATSON
Excavation/Setback/Form/Re-Bar 12/3/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 12/3/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 12/10/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 2/23/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 2/23/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 2/28/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Rough 2/28/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Rough 2/28/2022 Approved CHRISTOPHER DELLEFIELD
Sewer 2/28/2022 Approved CHRISTOPHER DELLEFIELD
Wood Frame 2/28/2022 Corrections Issued CHRISTOPHER DELLEFIELD
HVAC-Rough 3/15/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Wood Frame 3/15/2022 Partial Approval CHRISTOPHER DELLEFIELD
HVAC-Rough 4/8/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 4/8/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/8/2022 Conditional Approval CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 5/3/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Insulation 5/3/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Deputy Wood Construction 5/6/2022 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 5/6/2022 Approved CHRISTOPHER DELLEFIELD
Insulation 5/6/2022 Approved CHRISTOPHER DELLEFIELD
Drywall Nailing 5/20/2022 Not Ready for Inspection WILLIAM WREN
Drywall Nailing 5/25/2022 Partial Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/25/2022 Approved CHRISTOPHER DELLEFIELD
Pre-Inspection 6/13/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Shower Pan 6/13/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/14/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/22/2022 Approved MATTHEW NELSON
ELECTRICAL-Final 11/22/2022 Not Ready for Inspection MATTHEW NELSON
Final 11/22/2022 Corrections Issued MATTHEW NELSON
HVAC-Final 11/22/2022 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 11/22/2022 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 11/22/2022 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 1/24/2023 Approved MATTHEW NELSON
ELECTRICAL-Final 2/3/2023 Approved JOHN COLEMAN
Final 2/3/2023 OK to Issue CofO JOHN COLEMAN
HVAC-Final 2/3/2023 Approved JOHN COLEMAN
PLUMBING-Final 2/3/2023 Approved JOHN COLEMAN
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Approved JOHN COLEMAN
Service/Power Release 2/3/2023 Approved JOHN COLEMAN
Smoke Detectors 2/3/2023 Approved JOHN COLEMAN