11331-11333 W SATICOY ST 91352
Certificate Information: 11331-11333 W SATICOY ST 91352
- Application / Permit
- 21014-20000-02486
- Plan Check / Job No.
- B21VN06142
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert existing attached garage into ADU with addition,new ATTACHED ADU PER ORDINANCE
- Permit Issued
- Issued on 7/22/2021
- Issuing Office
- Current Status
- CofO Issued on 3/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2021 | RARES BODEA |
| Corrections Issued | 5/24/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 6/3/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 6/14/2021 | JOE VO |
| Plan Check Approved | 6/24/2021 | JOE VO |
| Issued | 7/22/2021 | APPLICANT |
| CofO in Progress | 2/6/2023 | JOHN COLEMAN |
| CofO Issued | 3/2/2023 | MICHAEL SMITH |
| Permit Finaled | 3/2/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/25/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/1/2021 | GABRIEL ROBLES |
| Clean Up Green Up | Cleared | 6/10/2021 | TERRI OSBORNE |
| ZA Case | Cleared | 6/10/2021 | TERRI OSBORNE |
| ZA Case | Cleared | 6/10/2021 | TERRI OSBORNE |
| Roof/Waste drainage to street | Cleared | 6/15/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/16/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 9/16/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 11/22/2021 | No Access for Inspection | WILLIAM KUEHN |
| Excavation/Setback/Form/Re-Bar | 11/23/2021 | Corrections Issued | DAVID MATSON |
| Footing/Foundation/Slab | 11/23/2021 | Not Ready for Inspection | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 12/3/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 12/3/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 12/10/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/23/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 2/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 2/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Sewer | 2/28/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Wood Frame | 2/28/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 3/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Wood Frame | 3/15/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 4/8/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/8/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Insulation | 5/3/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Deputy Wood Construction | 5/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 5/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/20/2022 | Not Ready for Inspection | WILLIAM WREN |
| Drywall Nailing | 5/25/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Pre-Inspection | 6/13/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Shower Pan | 6/13/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 7/14/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 11/22/2022 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 11/22/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 11/22/2022 | Corrections Issued | MATTHEW NELSON |
| HVAC-Final | 11/22/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Final | 11/22/2022 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 11/22/2022 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 1/24/2023 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 2/3/2023 | Approved | JOHN COLEMAN |
| Final | 2/3/2023 | OK to Issue CofO | JOHN COLEMAN |
| HVAC-Final | 2/3/2023 | Approved | JOHN COLEMAN |
| PLUMBING-Final | 2/3/2023 | Approved | JOHN COLEMAN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2023 | SGSOV Approved | JOHN COLEMAN |
| Service/Power Release | 2/3/2023 | Approved | JOHN COLEMAN |
| Smoke Detectors | 2/3/2023 | Approved | JOHN COLEMAN |