5926 N TOBIAS AVE 91411
Certificate Information: 5926 N TOBIAS AVE 91411
- Application / Permit
- 21014-20000-02477
- Plan Check / Job No.
- B21VN06097
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ECPC: ADDITION TO AND CONVERT THE (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). THE LID CLEARANCE HAS BEEN DEFERRED. APPROVAL FOR LID REQUIREMENTS SHALL BE OBTAINED FROM LASAN PRIOR TO THE ISSUANCE OF THE CERTIFICATE OF OCCUPANCY.
- Permit Issued
- Issued on 11/29/2021
- Issuing Office
- Current Status
- CofO Issued on 8/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/25/2021 | JESSE ARELLANO |
| Corrections Issued | 5/29/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 10/29/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 11/16/2021 | JESSE ARELLANO |
| Issued | 11/29/2021 | APPLICANT |
| Building Plans Picked Up | 11/30/2021 | APPLICANT |
| CofO in Progress | 8/17/2022 | RICHARD DOCKUS |
| CofO Issued | 8/17/2022 | MICHAEL SMITH |
| Permit Finaled | 8/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 6/4/2021 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 6/16/2021 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 10/29/2021 | JESSE ARELLANO |
| Roof/Waste drainage to street | Cleared | 11/2/2021 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/30/2021 | Not Ready for Inspection | MICHAEL TEMPLE |
| Underground Mechanical | 11/30/2021 | Partial Approval | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 12/3/2021 | Approved | WILLIAM KUEHN |
| BUILDING-Rough-Frame | 12/22/2021 | Partial Approval | RICHARD DOCKUS |
| ELECTRICAL-Rough | 12/22/2021 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 12/22/2021 | Approved | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 12/27/2021 | Approved | RICHARD DOCKUS |
| Green Building Rough | 12/27/2021 | Approved | RICHARD DOCKUS |
| HVAC-Rough | 12/27/2021 | Approved | RICHARD DOCKUS |
| Insulation | 12/29/2021 | Corrections Issued | ALAN MORELOS |
| Interior/Exterior Lathing | 12/29/2021 | Partial Approval | ALAN MORELOS |
| Insulation | 1/4/2022 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/13/2022 | Approved | RICHARD DOCKUS |
| Shower Pan | 1/18/2022 | Approved | RICHARD DOCKUS |
| Final | 2/22/2022 | Corrections Issued | RICHARD DOCKUS |
| Green Building Final | 2/22/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 2/22/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 2/22/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Final | 8/2/2022 | Approved | RICHARD DOCKUS |
| Final | 8/15/2022 | OK to Issue CofO | RICHARD DOCKUS |