8401 N DELCO AVE 91306
Certificate Information: 8401 N DELCO AVE 91306
- Application / Permit
- 21014-20000-02468
- Plan Check / Job No.
- B21VN06073
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION OF A 250 SQ. FT. ALUMINUM PATIO COVER PER ESR-2676P WITH ELECTRICAL
- Permit Issued
- Issued on 6/11/2021
- Issuing Office
- Current Status
- CofO Issued on 2/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/18/2021 | OMAR GARNICA |
| Corrections Issued | 5/18/2021 | OMAR GARNICA |
| Plan Check Approved | 6/11/2021 | OMAR GARNICA |
| Issued | 6/11/2021 | APPLICANT |
| Building Plans Picked Up | 6/16/2021 | APPLICANT |
| CofO in Progress | 1/3/2022 | PETER FOLLING |
| Permit Finaled | 2/16/2023 | DANIEL ORRANTE |
| CofO Issued | 2/16/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/16/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/1/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/1/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | 21204 VANOWEN STREET CANOGA PARK, CA 91303 |
| Engineer | Putnam,, Carl Matthew; Lic. No.: C68139 | 3441 IVYLINK PL LYNCHBURG, VA 24503 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 8/12/2021 | Corrections Issued | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 12/14/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Final | 12/14/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Footing/Foundation/Slab | 12/14/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 12/29/2021 | Approved | PETER FOLLING |
| ELECTRICAL-Rough | 12/29/2021 | Approved | PETER FOLLING |
| Final | 12/29/2021 | Not Ready for Inspection | PETER FOLLING |
| Footing/Foundation/Slab | 12/29/2021 | Approved | PETER FOLLING |
| Smoke Detectors | 12/29/2021 | Approved | PETER FOLLING |
| Final | 12/30/2021 | OK to Issue CofO | PETER FOLLING |