13123 W DESMOND ST 91331
Certificate Information: 13123 W DESMOND ST 91331
- Application / Permit
- 21014-20000-02465
- Plan Check / Job No.
- B21VN06056
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR ADDITION TO SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 1/4/2022
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | JOE VO |
| Corrections Issued | 7/2/2021 | JOE VO |
| Quality Review Completed | 7/14/2021 | MICHAEL PEREZ |
| Plan Check Approved | 8/25/2021 | JOE VO |
| Issued | 1/4/2022 | APPLICANT |
| CofO in Progress | 11/16/2022 | MICHEL ABAJAN |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
| CofO Issued | 11/19/2022 | MICHAEL SMITH |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/21/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 8/23/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 8/23/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/17/2022 | No Access for Inspection | MICHEL ABAJAN |
| Footing/Foundation/Slab | 3/17/2022 | Approved | MICHEL ABAJAN |
| Wood Frame | 3/29/2022 | Partial Approval | MICHAEL TEMPLE |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2022 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 7/14/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 7/14/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 7/14/2022 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 7/14/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 7/14/2022 | Approved | MICHEL ABAJAN |
| Shower Pan | 7/25/2022 | Approved | MICHEL ABAJAN |
| Insulation | 7/26/2022 | Conditional Approval | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/26/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 8/4/2022 | Approved | ARAM AVEDISIAN |
| Final | 11/7/2022 | Corrections Issued | MICHEL ABAJAN |
| MERV13>=Final | 11/7/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/7/2022 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 11/7/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/15/2022 | Approved | MICHEL ABAJAN |
| Final | 11/15/2022 | OK to Issue CofO | MICHEL ABAJAN |
| HVAC-Final | 11/15/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 11/15/2022 | Approved | MICHEL ABAJAN |