17414-17416 W DEVONSHIRE ST 91325
Certificate Information: 17414-17416 W DEVONSHIRE ST 91325
- Application / Permit
- 21014-20000-02464
- Plan Check / Job No.
- B21VN06053
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan ADU CONVERT EXISTING ATTACHED DEN/REC ROOM (391 S.F.)/CARPORT (445 SF) INTO AN ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(A).
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- CofO Issued on 9/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2021 | MICHAEL LOPEZ |
| Corrections Issued | 5/24/2021 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 7/27/2021 | MICHAEL LOPEZ |
| Plan Check Approved | 11/23/2021 | MICHAEL LOPEZ |
| Issued | 12/2/2021 | APPLICANT |
| CofO in Progress | 7/30/2024 | JAVIER RAMOS JR |
| Permit Finaled | 9/10/2024 | DANIEL ORRANTE |
| CofO Issued | 9/10/2024 | DANIEL ORRANTE |
| Permit Finaled | 9/10/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 6/16/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/16/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/16/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/16/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 11/18/2021 | TA ANH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baluyut,, Agustin Pangilinan; Lic. No.: C66025 | 22828 S CYPRESS DR CARSON, CA 90745 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/20/2022 | Not Ready for Inspection | RAUL OLAGI |
| PLUMBING-Rough | 5/20/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 5/24/2022 | Partial Approval | JAVIER RAMOS JR |
| Excavation/Setback/Form/Re-Bar | 6/3/2022 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/3/2022 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 11/17/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 5/5/2023 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2023 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 6/27/2023 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 6/27/2023 | Approved | JAVIER RAMOS JR |
| Sewer | 6/27/2023 | Approved | JAVIER RAMOS JR |
| Underground Mechanical | 6/27/2023 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 7/6/2023 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 7/6/2023 | Approved | JAVIER RAMOS JR |
| Pre-Inspection | 7/6/2023 | Approved | JAVIER RAMOS JR |
| Insulation | 8/15/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 8/15/2023 | Approved | JAVIER RAMOS JR |
| Shower Pan | 8/15/2023 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 8/18/2023 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 7/5/2024 | Approved | JENNIFER RABUCHIN |
| Final | 7/5/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/5/2024 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 7/5/2024 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/5/2024 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 7/5/2024 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/9/2024 | Partial Inspection | JAVIER RAMOS JR |
| Final | 7/9/2024 | Corrections Issued | JAVIER RAMOS JR |
| HVAC-Final | 7/9/2024 | Approved | JAVIER RAMOS JR |
| PLUMBING-Final | 7/9/2024 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/9/2024 | SGSOV Not Required | JAVIER RAMOS JR |
| ELECTRICAL-Final | 7/29/2024 | Approved | JAVIER RAMOS JR |
| Final | 7/29/2024 | OK to Issue CofO | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 7/29/2024 | SGSOV Approved | JAVIER RAMOS JR |
| Service/Power Release | 8/6/2024 | Approved | JAVIER RAMOS JR |