11740 N FELLOWS AVE 91331
Certificate Information: 11740 N FELLOWS AVE 91331
- Application / Permit
- 21014-20000-02461
- Plan Check / Job No.
- B21VN06050
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePLAN CHECK* PROPOSED 2ND FLOOR AND GROUND FLOOR ADDITION TO EXISTING DETACHED GARAGE TO CREATE AN ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 4/3/2023
- Issuing Office
- Current Status
- CofO Issued on 4/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/24/2021 | JOE VO |
| Corrections Issued | 7/2/2021 | JOE VO |
| Quality Review Completed | 7/7/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 9/7/2021 | JOE VO |
| Plan Check Approved | 3/22/2023 | MICHAEL LOPEZ |
| Issued | 4/3/2023 | APPLICANT |
| CofO in Progress | 3/13/2025 | MICHEL ABAJAN |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
| Permit Finaled | 4/1/2025 | RUBEN SALAS |
| CofO Issued | 4/1/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 11/22/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/22/2021 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 8/15/2022 | RUEL COLE |
| Miscellaneous | Cleared | 9/7/2022 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 9/7/2022 | MIGUEL GAMBOA |
| Low Impact Development | Cleared | 10/11/2022 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 10/13/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Saiyadian, Sarnaghi, Tomik; Lic. No.: C89129 | 1171 JUSTIN AVE APT 3 GLENDALE, CA 91201 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/14/2023 | Partial Approval | MICHEL ABAJAN |
| Deputy Drilled-In Anchors | 4/18/2023 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/26/2023 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 6/5/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/23/2023 | Corrections Issued | ROBERT GOLD |
| Green Building Rough | 6/23/2023 | Not Ready for Inspection | ROBERT GOLD |
| MERV13>=Rough | 6/23/2023 | Not Ready for Inspection | ROBERT GOLD |
| BUILDING-Rough-Frame | 11/21/2023 | Corrections Issued | MICHEL ABAJAN |
| ELECTRICAL-Rough | 11/21/2023 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/21/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Rough | 11/21/2023 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 11/21/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/19/2023 | Corrections Issued | MICHEL ABAJAN |
| Green Building Rough | 12/19/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Shower Pan | 12/19/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| Shower Pan | 12/21/2023 | Approved | MICHEL ABAJAN |
| Wood Frame | 12/21/2023 | Approved | MICHEL ABAJAN |
| Insulation | 12/27/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/27/2023 | Conditional Approval | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/29/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 1/17/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 11/18/2024 | Approved | MICHEL ABAJAN |
| Final | 11/18/2024 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 11/18/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 11/18/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 11/18/2024 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2024 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 11/18/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 2/25/2025 | Approved | MICHEL ABAJAN |
| Final | 2/25/2025 | Corrections Issued | MICHEL ABAJAN |
| HVAC-Final | 2/25/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 2/25/2025 | Approved | MICHEL ABAJAN |
| Final | 3/12/2025 | OK to Issue CofO | MICHEL ABAJAN |