5915 N GOODLAND AVE 91607
Certificate Information: 5915 N GOODLAND AVE 91607
- Application / Permit
- 21014-20000-02449
- Plan Check / Job No.
- B21VN06022
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 13'-2" X 22'-6" 2-STORY ADDITION TO (E) DETACHED GARAGE FOR (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/10/2022
- Issuing Office
- Current Status
- CofO Issued on 2/4/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | RAPHAEL ROSAS |
| Corrections Issued | 5/22/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 1/26/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| Issued | 2/10/2022 | APPLICANT |
| CofO in Progress | 1/31/2023 | KIRK SANDERS |
| CofO Issued | 2/4/2023 | MICHAEL SMITH |
| Permit Finaled | 2/4/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 1/7/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/7/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Meichtry S P Const; Lic. No.: 500276-B | 7300 CAPISTRANO AVENUE WEST HILLS, CA 91307 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21500 WYANDOTTE ST 106 CANOGA PARK, CA 91303 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/17/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 5/23/2022 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/23/2022 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 5/23/2022 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 6/10/2022 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 7/29/2022 | Partial Approval | RAFAEL CORTES |
| ELECTRICAL-Rough | 7/29/2022 | Approved | RAFAEL CORTES |
| Green Building Rough | 7/29/2022 | Approved | RAFAEL CORTES |
| HVAC-Rough | 7/29/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Rough | 7/29/2022 | Approved | RAFAEL CORTES |
| Deputy Wood Construction | 8/1/2022 | Conditional Approval | MATT KELLERMAN |
| Insulation | 8/8/2022 | Approved | RAFAEL CORTES |
| Interior/Exterior Lathing | 8/8/2022 | Approved | RAFAEL CORTES |
| Drywall Nailing | 8/29/2022 | Approved | ASHLEY THOMPSON |
| Underground Mechanical | 9/30/2022 | Corrections Issued | ALAN MORELOS |
| Underground Mechanical | 10/17/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 10/27/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 12/19/2022 | Approved | MISAEL ESPARZA |
| Final | 12/19/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 12/19/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 12/19/2022 | Approved | MISAEL ESPARZA |
| Final | 1/30/2023 | OK to Issue CofO | KIRK SANDERS |
| Green Building Final | 1/30/2023 | Approved | KIRK SANDERS |