3020 S NORTON AVE 90018
Certificate Information: 3020 S NORTON AVE 90018
- Application / Permit
- 21014-20000-02435
- Plan Check / Job No.
- B21VN05991
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 38'-10" x 16'-6" IRREGULAR SHAPE ADDITION TO (E) SFD FOR TWO BEDROOMS AND TWO BATHROOMS. REMODEL (E) KITCHEN, BEDROOM, AND BATHROOM. WORK PER ENGINEER. BUILDING SHALL BE FULLY SPRINKLERED NFPA 13D.
- Permit Issued
- Issued on 12/15/2021
- Issuing Office
- Current Status
- CofO Issued on 4/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | ROSENDO MEDINA |
| Corrections Issued | 5/22/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 11/8/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 11/30/2021 | ROSENDO MEDINA |
| Plan Check Approved | 12/15/2021 | ROSENDO MEDINA |
| Issued | 12/15/2021 | APPLICANT |
| Building Plans Picked Up | 12/16/2021 | APPLICANT |
| CofO in Progress | 3/28/2023 | CALEB MEISTER |
| Permit Finaled | 4/2/2023 | DEROLD HAUFF |
| CofO Issued | 4/2/2023 | DEROLD HAUFF |
| Permit Finaled | 4/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/23/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2021 | CECILIO NAVARRO |
| Low Impact Development | Cleared | 10/29/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/8/2021 | JEANETTE VONG |
Contact Information
| Contractor | Builders & Son'S Inc; Lic. No.: 961171-B | 8720 VENICE BLVD STE 208 LOS ANGELES, CA 90034 |
| Engineer | Hoerner,, John Brent; Lic. No.: S2145 | 24024 VIA CANDELA VALENCIA, CA 91355 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/16/2021 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/15/2022 | Conditional Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/15/2022 | Approved | STUART CHAPMAN |
| Final | 6/15/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 6/15/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 6/15/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 6/15/2022 | Approved | STUART CHAPMAN |
| Insulation | 7/1/2022 | Corrections Issued | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/1/2022 | Partial Approval | STUART CHAPMAN |
| Shower Pan | 7/1/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/5/2022 | Partial Approval | STUART CHAPMAN |
| Drywall Nailing | 7/8/2022 | Corrections Issued | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/12/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 2/21/2023 | Approved | CALEB MEISTER |
| Final | 2/21/2023 | Corrections Issued | CALEB MEISTER |
| Green Building Final | 2/21/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 2/21/2023 | Approved | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 2/21/2023 | SGSOV Approved | CALEB MEISTER |
| Smoke Detectors | 2/21/2023 | Approved | CALEB MEISTER |
| Final | 3/28/2023 | OK to Issue CofO | CALEB MEISTER |