12333 W SUNSET BLVD 90049
Certificate Information: 12333 W SUNSET BLVD 90049
- Application / Permit
- 21014-20000-02426
- Plan Check / Job No.
- B21VN05952
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- IRR. SHAPED ADDITION TO THE FRONT, EAST SIDE AND REAR OF (E) SINGLE FAMILY DWELLING AND MAJOR REMODEL; AUTOMATIC SPRINKLER SYSTEM IS REQUIRED; ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 1/3/2022
- Issuing Office
- Current Status
- CofO Issued on 10/12/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | SEAN SHAHMIRI |
| Corrections Issued | 6/24/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 7/2/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/7/2021 | APPLICANT |
| Applicant returned to address corrections | 11/22/2021 | SEAN SHAHMIRI |
| Plan Check Approved | 12/13/2021 | SEAN SHAHMIRI |
| Issued | 1/3/2022 | APPLICANT |
| CofO in Progress | 10/10/2023 | KENNETH NAGLE |
| CofO in Progress | 10/11/2023 | KENNETH NAGLE |
| Permit Finaled | 10/12/2023 | DANIEL ORRANTE |
| CofO Issued | 10/12/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/12/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 7/14/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 7/14/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 7/14/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 7/14/2021 | DINAH GARIN |
| Sewer availability | Cleared | 7/14/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2021 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 9/3/2021 | KURT CORRAL |
| Low Impact Development | Cleared | 11/1/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 11/2/2021 | DINAH GARIN |
Contact Information
| Architect | Gold,, Kerry Daniel; Lic. No.: C13781 | 638 LINDERO CYN RD # 432 OAK PARK, CA 91377 |
| Contractor | Owner-Builder | , |
| Engineer | Sayah,, Daniel H; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/22/2022 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/22/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 7/21/2022 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 7/21/2022 | Partial Approval | JUAN VALENZUELA |
| Insulation | 7/22/2022 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2022 | Partial Approval | JUAN VALENZUELA |
| Special/Order Compliance | 10/27/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 12/6/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 12/6/2022 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 12/6/2022 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Rough | 12/6/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 12/6/2022 | Not Ready for Inspection | DAVID FEILER |
| Verify Sprinkler Sign Off | 12/6/2022 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 12/8/2022 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 12/8/2022 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 12/15/2022 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 12/15/2022 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 12/15/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 12/15/2022 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 12/15/2022 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Rough | 12/16/2022 | Conditional Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/19/2022 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 12/19/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 12/19/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 12/28/2022 | Partial Approval | KEVIN SARGSYAN |
| Shower Pan | 12/28/2022 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/1/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Green Building Rough | 2/1/2023 | Not Ready for Inspection | KEVIN SARGSYAN |
| Shower Pan | 2/1/2023 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 2/15/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 2/15/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/15/2023 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 2/23/2023 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 2/23/2023 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 3/24/2023 | Approved | JESUS PINEDA |
| Gas Test | 6/22/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 6/22/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 6/22/2023 | Corrections Issued | HERBERT GIRON |
| Final | 9/5/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/5/2023 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Final | 9/18/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 9/18/2023 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 9/18/2023 | SGSOV Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/18/2023 | Approved | OGANES TARAKHCHYAN |
| Final | 9/28/2023 | Conditional Approval | KENNETH NAGLE |
| Final | 10/10/2023 | OK to Issue CofO | KENNETH NAGLE |
| Service/Power Release | 10/10/2023 | Approved | KENNETH NAGLE |