11024 N NOBLE AVE 91345
Certificate Information: 11024 N NOBLE AVE 91345
- Application / Permit
- 21014-20000-02420
- Plan Check / Job No.
- B21VN05931
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 21' x 19' ADDITION FOR NEW BEDROOM AND BATHROOM. REMODEL (E) BEDROOMS AND BATHROOMS. NEW 21'-11" x 14' SOLID PATIO COVER ADDITION. WORK PER ENGINEER.
- Permit Issued
- Issued on 2/11/2022
- Issuing Office
- Current Status
- CofO Issued on 12/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | ROSENDO MEDINA |
| Corrections Issued | 5/22/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 11/10/2021 | ROSENDO MEDINA |
| Applicant returned to address corrections | 1/27/2022 | ROSENDO MEDINA |
| Plan Check Approved | 2/1/2022 | ROSENDO MEDINA |
| Building Plans Picked Up | 2/2/2022 | APPLICANT |
| Issued | 2/11/2022 | APPLICANT |
| CofO in Progress | 10/19/2023 | JENNIFER RABUCHIN |
| Permit Finaled | 12/21/2023 | RUBEN SALAS |
| CofO Issued | 12/21/2023 | RUBEN SALAS |
| Permit Finaled | 12/21/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/21/2021 | TINA MIRANDA |
| Construction within easement | Cleared | 10/21/2021 | TINA MIRANDA |
| Low Impact Development | Cleared | 1/13/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 1/28/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/1/2022 | DAGOVERTO GUERRERO |
| Miscellaneous | Cleared | 2/1/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/1/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Azarbin,, Hamid; Lic. No.: C64515 | 22655 COVELLO ST WEST HILLS, CA 91307 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/9/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/27/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 5/27/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 6/3/2022 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 6/3/2022 | Partial Approval | JENNIFER RABUCHIN |
| Wood Frame | 6/3/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/6/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Rough | 9/6/2022 | Not Ready for Inspection | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/20/2022 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/20/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 9/20/2022 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 9/20/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 9/29/2022 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/29/2022 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 10/28/2022 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 12/16/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 12/30/2022 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 9/29/2023 | Approved | RYAN SALAZAR |
| Final | 9/29/2023 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 9/29/2023 | Approved | RYAN SALAZAR |
| Green Building Final | 9/29/2023 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/29/2023 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 9/29/2023 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 9/29/2023 | Approved | RYAN SALAZAR |
| ELECTRICAL-Final | 10/19/2023 | Approved | JENNIFER RABUCHIN |
| Final | 10/19/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 10/19/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 10/19/2023 | Approved | JENNIFER RABUCHIN |