8017 N WISNER AVE 91402
Certificate Information: 8017 N WISNER AVE 91402
- Application / Permit
- 21014-20000-02398
- Plan Check / Job No.
- B21VN05880
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 40'-9" X 18' IRREGULAR SHAPPED ADDITION TO THE (E) SFD. ALL WORK PER WFPP. FIRE SPRINKLER NFPA 13-D THRU-OUT BUILDING IS REQUIRED.
- Permit Issued
- Issued on 2/28/2022
- Issuing Office
- Current Status
- Issued on 2/28/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | PARISA ZAHABI |
| Corrections Issued | 5/22/2021 | PARISA ZAHABI |
| Applicant returned to address corrections | 8/18/2021 | PARISA ZAHABI |
| Plan Check Approved | 1/11/2022 | ALFREDO JARA |
| Building Plans Picked Up | 1/12/2022 | APPLICANT |
| Issued | 2/28/2022 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/1/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 6/3/2021 | GABRIEL ROBLES |
| CPC | Cleared | 6/9/2021 | DANG NGUYEN |
| Hydrant and Access approval | Cleared | 7/30/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/10/2021 | JONATAN VELASQUEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/12/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 6/1/2022 | Corrections Issued | GREGG CUMMINGS |
| Wood Frame | 6/1/2022 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/7/2022 | Partial Approval | GREGG CUMMINGS |
| Insulation | 6/7/2022 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 6/7/2022 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 6/13/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 7/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 7/27/2022 | Approved | GREGG CUMMINGS |
| Wood Frame | 7/27/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/20/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 10/20/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/13/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 12/13/2022 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/19/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Shower Pan | 12/19/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 1/9/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/2/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 2/2/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 2/2/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 3/21/2023 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 3/21/2023 | Approved | JENNIFER RABUCHIN |