9667 N SALUDA AVE 91042
Certificate Information: 9667 N SALUDA AVE 91042
- Application / Permit
- 21014-20000-02395
- Plan Check / Job No.
- B21VN05869
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 400 SQ. FT. 2-CAR GARAGE TO ACCESSORY DWELLING UNIT WITH 600 SQ. FT. ADDITION PER LAMC 12.22A33 (c)-(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 2/17/2022
- Issuing Office
- Current Status
- CofO Issued on 9/3/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 7/1/2021 | COLIN LOREDO |
| Corrections Issued | 7/8/2021 | COLIN LOREDO |
| Quality Review Completed | 7/16/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/16/2021 | APPLICANT |
| Applicant returned to address corrections | 2/14/2022 | COLIN LOREDO |
| Plan Check Approved | 2/17/2022 | COLIN LOREDO |
| Issued | 2/17/2022 | APPLICANT |
| CofO in Progress | 8/25/2022 | MATTHEW NELSON |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
| CofO Issued | 9/3/2022 | MICHAEL SMITH |
| Permit Finaled | 9/3/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 8/2/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 8/2/2021 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 10/20/2021 | TIMOTHY POWELL |
| Construction near power lines | Cleared | 1/11/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 1/31/2022 | NICK RAYGOZA |
| Roof/Waste drainage to street | Cleared | 2/1/2022 | ABDULLAH SADOZAI |
| GPI Written Notices | Cleared | 2/14/2022 | COLIN LOREDO |
Contact Information
| Contractor | Markarian Setrag; Lic. No.: 832632-B | 1162 FLORENCE ST IMPERIAL BEACH, CA 91932 |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/23/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Underground Mechanical | 2/23/2022 | Partial Approval | MATTHEW NELSON |
| Excavation/Setback/Form/Re-Bar | 2/25/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/19/2022 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 4/19/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/19/2022 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Rough | 4/19/2022 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 4/19/2022 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/22/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 4/22/2022 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 4/22/2022 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 4/22/2022 | Approved | MATTHEW NELSON |
| Insulation | 4/28/2022 | Approved | MATTHEW NELSON |
| Shower Pan | 4/28/2022 | Approved | MATTHEW NELSON |
| Drywall Nailing | 5/2/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 5/2/2022 | Partial Approval | ASHLEY THOMPSON |
| Final | 6/28/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Footing/Foundation/Slab | 6/28/2022 | Approved | MATTHEW NELSON |
| Green Building Final | 6/28/2022 | Not Ready for Inspection | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 6/28/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 6/28/2022 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Final | 8/18/2022 | Not Ready for Inspection | MATTHEW NELSON |
| HVAC-Final | 8/18/2022 | Approved | MATTHEW NELSON |
| PLUMBING-Final | 8/18/2022 | Approved | MATTHEW NELSON |
| Final | 8/19/2022 | Partial Approval | MATTHEW NELSON |
| Green Building Final | 8/19/2022 | Approved | MATTHEW NELSON |
| Smoke Detectors | 8/19/2022 | Approved | MATTHEW NELSON |
| Final | 8/24/2022 | OK to Issue CofO | MATTHEW NELSON |