13129 W OTSEGO ST 91423
Certificate Information: 13129 W OTSEGO ST 91423
- Application / Permit
- 21014-20000-02393
- Plan Check / Job No.
- B21VN05864
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION OF (31'-0" x 58'-2"),1224 SQFT AND INTERIOR REMODEL TO (E) SFD W/NFPA 13D SPRINKLERS THROUGHOUT LOT. SEE COMMENTS.
- Permit Issued
- Issued on 3/21/2022
- Issuing Office
- Current Status
- CofO Issued on 3/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | PETER MOSESIAN |
| Corrections Issued | 6/20/2021 | PETER MOSESIAN |
| Quality Review Completed | 7/7/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/13/2021 | APPLICANT |
| Applicant returned to address corrections | 2/15/2022 | PETER MOSESIAN |
| Plan Check Approved | 3/3/2022 | PETER MOSESIAN |
| Issued | 3/21/2022 | APPLICANT |
| CofO in Progress | 3/2/2023 | KIRK SANDERS |
| CofO Issued | 3/13/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/13/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 2/15/2022 | MITESH PATEL |
| Eng Process Fee Ord 176,300 | Cleared | 2/18/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 2/18/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/18/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Aguilar Don; Lic. No.: 635651-B | 7762 SHADY SPRING DRIVE BURBANK, CA 91504 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 21757 DEVONSHIRE ST. SUITE 3 CANOGA PARK, CA 91311 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/7/2022 | Partial Approval | MATT KELLERMAN |
| Underground Mechanical | 4/7/2022 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 4/13/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 4/19/2022 | Approved | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 4/19/2022 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 4/19/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/5/2022 | Partial Approval | RICHARD DOCKUS |
| Sewer | 5/5/2022 | Approved | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 5/18/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 5/25/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 5/25/2022 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 5/25/2022 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 5/25/2022 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 5/25/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/1/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 6/6/2022 | Conditional Approval | CALEB MEISTER |
| Shower Pan | 6/6/2022 | Not Ready for Inspection | CALEB MEISTER |
| Drywall Nailing | 6/10/2022 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 6/10/2022 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/28/2022 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 6/29/2022 | Approved | RAFAEL CORTES |
| Interior/Exterior Lathing | 6/29/2022 | Off-Hour Fees Due | |
| Deputy Drilled-In Anchors | 8/23/2022 | Approved | RAFAEL CORTES |
| Deputy Drilled-In Anchors | 9/22/2022 | Conditional Approval | RAFAEL CORTES |
| Deputy Wood Construction | 9/27/2022 | Conditional Approval | RAFAEL CORTES |
| Gas Test | 11/16/2022 | Approved | DANIEL ORRANTE |
| BUILDING-Rough-Frame | 12/6/2022 | Approved | KIRK SANDERS |
| Final | 12/6/2022 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 12/6/2022 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 12/6/2022 | Approved | KIRK SANDERS |
| Final | 12/14/2022 | Corrections Issued | JOHN HAYES |
| Final | 1/13/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 2/15/2023 | Not Ready for Inspection | KIRK SANDERS |
| Final | 3/1/2023 | OK to Issue CofO | KIRK SANDERS |