11084 W WICKS ST 91352
Certificate Information: 11084 W WICKS ST 91352
- Application / Permit
- 21014-20000-02388
- Plan Check / Job No.
- B21VN05850
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXTEND (E) FAMILY/LIVING ROOM (IRR 32' X 16'-7") TO (E) 1-STORY SFD
- Permit Issued
- Issued on 4/20/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/17/2021 | COLIN LOREDO |
| Corrections Issued | 6/21/2021 | COLIN LOREDO |
| Quality Review Completed | 7/7/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 7/12/2021 | APPLICANT |
| Applicant returned to address corrections | 9/1/2022 | NILOOFAR MEHRAIN |
| Plan Check Approved | 4/12/2023 | NILOOFAR MEHRAIN |
| Issued | 4/20/2023 | APPLICANT |
| CofO in Progress | 4/12/2024 | DAVID ANDERSON |
| Permit Finaled | 5/10/2024 | RUBEN SALAS |
| CofO Issued | 5/10/2024 | RUBEN SALAS |
| Permit Finaled | 5/10/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 7/22/2021 | TIMOTHY POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 9/17/2021 | DAGOVERTO GUERRERO |
| GPI Written Notices | Cleared | 10/5/2021 | COLIN LOREDO |
| Low Impact Development | Cleared | 10/20/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 10/20/2021 | LEE GUILBEAUX |
| ZI | Cleared | 4/11/2023 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/16/2023 | Corrections Issued | DAVID ANDERSON |
| METHANE-Barrier | 6/16/2023 | Approved | DAVID ANDERSON |
| METHANE-Subgrade | 6/16/2023 | Approved | DAVID ANDERSON |
| Footing/Foundation/Slab | 6/28/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2023 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/5/2023 | Corrections Issued | DAVID ANDERSON |
| HVAC-Rough | 9/5/2023 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/11/2023 | Not Ready for Inspection | DAVID ANDERSON |
| HVAC-Rough | 9/11/2023 | Not Ready for Inspection | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/18/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 9/18/2023 | Approved | DAVID ANDERSON |
| Green Building Rough | 9/18/2023 | Approved | DAVID ANDERSON |
| HVAC-Rough | 9/18/2023 | Approved | DAVID ANDERSON |
| METHANE-Rough | 9/18/2023 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 9/21/2023 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Approved | DAVID ANDERSON |
| Wood Frame | 9/21/2023 | Approved | DAVID ANDERSON |
| Insulation | 10/16/2023 | Not Ready for Inspection | THOMAS FINNILA |
| Insulation | 10/19/2023 | Approved | DAVID ANDERSON |
| Drywall Nailing | 10/26/2023 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 10/26/2023 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 1/4/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 1/4/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Pre-Inspection | 2/27/2024 | No Access for Inspection | MATTHEW NELSON |
| Final | 2/28/2024 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 2/28/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/28/2024 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 2/28/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 4/11/2024 | OK to Issue CofO | DAVID ANDERSON |
| Smoke Detectors | 4/11/2024 | Approved | DAVID ANDERSON |