4458 N KATHERINE AVE 91423
Certificate Information: 4458 N KATHERINE AVE 91423
- Application / Permit
- 21014-20000-02387
- Plan Check / Job No.
- B21VN05847
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND 2ND STORY ADDITION TO (E) SINGLE FAMILY DWELING. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/27/2022
- Issuing Office
- Current Status
- CofO Issued on 5/23/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | COLIN LOREDO |
| Corrections Issued | 6/2/2021 | COLIN LOREDO |
| Quality Review Completed | 6/4/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 6/8/2021 | APPLICANT |
| Applicant returned to address corrections | 6/22/2021 | COLIN LOREDO |
| Plan Check Approved | 1/27/2022 | COLIN LOREDO |
| Issued | 1/27/2022 | APPLICANT |
| CofO in Progress | 5/22/2023 | ROBERT GOLD |
| Permit Finaled | 5/23/2023 | MICHAEL SMITH |
| CofO Issued | 5/23/2023 | MICHAEL SMITH |
| Permit Finaled | 5/23/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/1/2021 | GABRIEL ROBLES |
| ZI | Cleared | 10/25/2021 | LAUREN PADICK |
| Low Impact Development | Cleared | 12/14/2021 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 12/15/2021 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/28/2022 | Partial Approval | MISAEL ESPARZA |
| Underground Mechanical | 3/1/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Footing/Foundation/Slab | 3/9/2022 | Approved | MISAEL ESPARZA |
| Deputy Reinf. Concrete | 3/10/2022 | Conditional Approval | MISAEL ESPARZA |
| Wood Frame | 3/23/2022 | Partial Approval | MISAEL ESPARZA |
| Deputy Wood Construction | 4/12/2022 | Approved | MISAEL ESPARZA |
| Wood Frame | 4/12/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 4/22/2022 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 4/25/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 4/29/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/5/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 5/5/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| MERV13>=Rough | 5/5/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 5/9/2022 | Partial Approval | MISAEL ESPARZA |
| Insulation | 5/10/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 5/18/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| Green Building Rough | 5/18/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 5/19/2022 | Approved | MISAEL ESPARZA |
| Shower Pan | 5/24/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 5/27/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/8/2023 | Corrections Issued | MISAEL ESPARZA |
| Final | 5/8/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 5/8/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Final | 5/8/2023 | Corrections Issued | MISAEL ESPARZA |
| MERV13>=Final | 5/8/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 5/8/2023 | Corrections Issued | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/8/2023 | SGSOV Approved | MISAEL ESPARZA |
| Smoke Detectors | 5/8/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 5/15/2023 | Partial Approval | ROBERT GOLD |
| Gas Test | 5/15/2023 | Approved | ROBERT GOLD |
| HVAC-Final | 5/15/2023 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Final | 5/15/2023 | Partial Approval | ROBERT GOLD |
| Final | 5/19/2023 | OK to Issue CofO | ROBERT GOLD |
| Green Building Final | 5/19/2023 | Approved | ROBERT GOLD |
| MERV13>=Final | 5/19/2023 | Approved | ROBERT GOLD |
| Service/Power Release | 5/19/2023 | Approved | ROBERT GOLD |