13924 W ROSCOE BLVD 91402

Certificate Information: 13924 W ROSCOE BLVD 91402

Application / Permit
21014-20000-02386
Plan Check / Job No.
B21VN05841
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) GARAGE TO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c) AND (d) AND AN IRREGULAR 24'1" X 27'8" ADDITION. DESIGN PER WFPP. “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 11/5/2021
Issuing Office
Current Status
CofO Issued on 8/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/18/2021 APPLICANT
Assigned to Plan Check Engineer 5/29/2021 LUIS RINCON
Corrections Issued 5/29/2021 LUIS RINCON
Applicant returned to address corrections 9/3/2021 LUIS RINCON
Plan Check Approved 10/4/2021 PINANK PATEL
Building Plans Picked Up 10/5/2021 APPLICANT
Issued 11/5/2021 APPLICANT
CofO in Progress 8/12/2022 GREGG CUMMINGS
CofO Issued 8/27/2022 MICHAEL SMITH
Permit Finaled 8/27/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/9/2021 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 9/9/2021 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 9/9/2021 LEE GUILBEAUX
Sewer availability Cleared 9/14/2021 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 9/14/2021 LEE GUILBEAUX
Tenant Habitability Plan Cleared 9/15/2021 JEFFREY BULL

Contact Information

Contractor V V V Construction; Lic. No.: 1034103-B 534 N LOUISE STREET #_B      GLENDALE, CA 91206

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 11/10/2021 Corrections Issued WILLIAM WREN
PLUMBING-Rough 3/1/2022 Partial Approval GREGG CUMMINGS
Deputy Drilled-In Anchors 3/10/2022 Conditional Approval DAVID MATSON
Excavation/Setback/Form/Re-Bar 3/10/2022 Approved GREGG CUMMINGS
Footing/Foundation/Slab 3/10/2022 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 4/13/2022 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 4/13/2022 Not Ready for Inspection JOHN HAYES
HVAC-Rough 4/13/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 4/13/2022 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 4/21/2022 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 4/21/2022 Approved GREGG CUMMINGS
HVAC-Rough 4/21/2022 Approved GREGG CUMMINGS
PLUMBING-Rough 4/21/2022 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 5/2/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Rough 5/2/2022 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 5/2/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 5/6/2022 Approved GREGG CUMMINGS
Insulation 5/6/2022 Approved GREGG CUMMINGS
Shower Pan 5/9/2022 Approved WILLIAM WREN
Drywall Nailing 5/12/2022 Approved WILLIAM WREN
Interior/Exterior Lathing 5/12/2022 Approved WILLIAM WREN
Sewer 6/14/2022 Approved WILLIAM WREN
Underground Mechanical 6/14/2022 Approved WILLIAM WREN
Underground Mechanical 6/24/2022 Approved GREGG CUMMINGS
Final 8/4/2022 Corrections Issued GREGG CUMMINGS
Green Building Final 8/4/2022 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 8/4/2022 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 8/4/2022 Not Ready for Inspection GREGG CUMMINGS
Final 8/11/2022 Corrections Issued GREGG CUMMINGS
Smoke Detectors 8/11/2022 Approved GREGG CUMMINGS
ELECTRICAL-Final 8/12/2022 Approved GREGG CUMMINGS
Final 8/12/2022 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 8/12/2022 Approved GREGG CUMMINGS
PLUMBING-Final 8/12/2022 Approved GREGG CUMMINGS