15658 W ROMAR ST 91343

Certificate Information: 15658 W ROMAR ST 91343

Application / Permit
21014-20000-02381
Plan Check / Job No.
B21VN05820
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 13'-6" x 32'-0" ADDITION AT REAR OF (E) SINGLE FAMILY DWELLING TO ADD A NEW BEDROOM, BATHROOM AND DINING ROOM; ALL WORK PER WFPP
Permit Issued
Issued on 9/1/2021
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 5/12/2021 SEAN SHAHMIRI
Corrections Issued 5/15/2021 SEAN SHAHMIRI
Building Plans Picked Up 5/21/2021 APPLICANT
Plan Check Approved 8/31/2021 SEAN SHAHMIRI
Issued 9/1/2021 APPLICANT
CofO in Progress 8/23/2022 JAVIER RAMOS JR
CofO Issued 8/23/2022 MICHAEL SMITH
Permit Finaled 8/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Miscellaneous Cleared 5/27/2021 MARITZA PRZEKOP
Eng Process Fee Ord 176,300 Cleared 8/2/2021 GABRIEL ROBLES
Sewer availability Cleared 8/2/2021 GABRIEL ROBLES
Low Impact Development Cleared 8/23/2021 YVAINNE GALSIM
Roof/Waste drainage to street Cleared 8/24/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/28/2021 Conditional Approval MARK JOHNSON
Excavation/Setback/Form/Re-Bar 9/30/2021 Partial Approval MARK JOHNSON
Footing/Foundation/Slab 9/30/2021 Partial Approval MARK JOHNSON
Sewer 9/30/2021 Corrections Issued MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 11/3/2021 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 11/29/2021 Corrections Issued MARK JOHNSON
ELECTRICAL-Rough 11/29/2021 Corrections Issued MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 11/29/2021 Partial Approval MARK JOHNSON
Green Building Rough 11/29/2021 Approved MARK JOHNSON
MERV13>=Rough 11/29/2021 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 11/29/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 12/8/2021 Approved MARK JOHNSON
ELECTRICAL-Rough 12/8/2021 Approved MARK JOHNSON
Insulation 12/8/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 12/8/2021 Approved MARK JOHNSON
MERV13>=Rough 12/8/2021 Approved MARK JOHNSON
Drywall Nailing 12/17/2021 Approved JENNIFER RABUCHIN
Final 3/10/2022 Corrections Issued MICHAEL TEMPLE
Footing/Foundation/Slab 3/10/2022 Approved MICHAEL TEMPLE
Green Building Final 3/10/2022 Approved MICHAEL TEMPLE
MERV13>=Final 3/10/2022 Approved MICHAEL TEMPLE
SGSOV-Seismic Gas S/O Valve 3/10/2022 SGSOV Approved MICHAEL TEMPLE
Smoke Detectors 3/10/2022 Approved MICHAEL TEMPLE
Final 8/23/2022 OK to Issue CofO JAVIER RAMOS JR