5907-5909 N RADFORD AVE 91607

Certificate Information: 5907-5909 N RADFORD AVE 91607

Application / Permit
21014-20000-02379
Plan Check / Job No.
B21VN05812
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT ATTACHED GARAGE TO ACCESSORY DWELLING UNIT (329 SQ FT) PER LAMC 12.22 A.33(c) and (e). 29'-4" X 24'-8" IRREG SHAPED ADDITION TO (E) DWELLING TO ENLARGE KITCHEN AND ADD NEW BEDROOM, BATHROOM, CLOSET, AND LAUNDRY ROOM.
Permit Issued
Issued on 12/9/2021
Issuing Office
Current Status
CofO in Progress on 6/25/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 5/19/2021 JEROME MAGAT PALMA
Corrections Issued 5/19/2021 JEROME MAGAT PALMA
Plan Check Approved 12/6/2021 JEROME MAGAT PALMA
Building Plans Picked Up 12/8/2021 APPLICANT
Issued 12/9/2021 APPLICANT
No Progress 6/25/2026 ROBERTO PALACIOS-LOPEZ
CofO in Progress 6/25/2026 ROBERTO PALACIOS-LOPEZ

Permit Application Clearance Information

Address approval Cleared 5/27/2021 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 5/27/2021 DAGOVERTO GUERRERO
Sewer availability Cleared 5/27/2021 DAGOVERTO GUERRERO
Low Impact Development Cleared 11/24/2021 SUNG JOON WON
Roof/Waste drainage to street Cleared 11/24/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Chatsky,, German; Lic. No.: C84153 6541 ODESSA AVE UNIT 11      LAKE BALBOA, CA 91406

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/22/2021 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 1/3/2022 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 1/10/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 1/19/2022 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 1/24/2022 Partial Approval CALEB MEISTER
Insulation 1/27/2022 Partial Approval CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 1/27/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 2/1/2022 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 3/7/2022 Corrections Issued JACK KARGODORIAN
HVAC-Rough 3/7/2022 Approved JACK KARGODORIAN
PLUMBING-Rough 3/7/2022 Not Ready for Inspection JACK KARGODORIAN
BUILDING-Rough-Frame 3/9/2022 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 3/9/2022 Approved ARAM AVEDISIAN
Green Building Rough 3/9/2022 Approved ARAM AVEDISIAN
HVAC-Rough 3/9/2022 Approved ARAM AVEDISIAN
MERV13>=Rough 3/9/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 3/9/2022 Approved ARAM AVEDISIAN
Insulation 3/11/2022 Corrections Issued ARAM AVEDISIAN
Interior/Exterior Lathing 3/11/2022 Partial Approval ARAM AVEDISIAN
Shower Pan 3/11/2022 Approved ARAM AVEDISIAN
Drywall Nailing 3/25/2022 Not Ready for Inspection CALEB MEISTER
Interior/Exterior Lathing 4/13/2022 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 10/19/2023 Approved JOHN HAYES
Final 10/19/2023 Corrections Issued JOHN HAYES
Green Building Final 10/19/2023 Approved JOHN HAYES
Green Building Rough 10/19/2023 Approved JOHN HAYES
MERV13>=Final 10/19/2023 Approved JOHN HAYES
MERV13>=Rough 10/19/2023 Approved JOHN HAYES
SGSOV-Seismic Gas S/O Valve 10/19/2023 SGSOV Not Ready JOHN HAYES
Smoke Detectors 10/19/2023 Approved JOHN HAYES
Final 1/10/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 1/10/2025 SGSOV Not Ready ROBERTO PALACIOS-LOPEZ
Final 6/2/2026 Corrections Issued GAREN HAYRAPETYAN
SGSOV-Seismic Gas S/O Valve 6/2/2026 SGSOV Not Ready GAREN HAYRAPETYAN
Final 6/18/2026 Corrections Issued ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 6/18/2026 SGSOV Approved ROBERTO PALACIOS-LOPEZ
Final 6/25/2026 Conditional Approval ROBERTO PALACIOS-LOPEZ