7926 S AGNEW AVE 90045
Certificate Information: 7926 S AGNEW AVE 90045
- Application / Permit
- 21014-20000-02369
- Plan Check / Job No.
- B21VN05775
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 8'-11" X 8'-11" ADDITION AND REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 9/2/2021
- Issuing Office
- Current Status
- CofO Issued on 2/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2021 | RAPHAEL ROSAS |
| Corrections Issued | 5/20/2021 | RAPHAEL ROSAS |
| Plan Check Approved | 8/5/2021 | RAPHAEL ROSAS |
| Issued | 9/2/2021 | APPLICANT |
| Building Plans Picked Up | 9/3/2021 | APPLICANT |
| CofO in Progress | 1/27/2023 | BOBBY KEY |
| Permit Finaled | 2/6/2023 | DANIEL ORRANTE |
| CofO Issued | 2/6/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/6/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/28/2021 | DENNIS BRAGIN |
| Sewer availability | Cleared | 6/28/2021 | DENNIS BRAGIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/16/2021 | NIKTA MOUSAVI |
| Grading Pre-Inspection | Cleared | 8/5/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | Md Electrical Services Inc; Lic. No.: 972173-B | 7520 BRADWELL AVENUE WHITTIER, CA 90606 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/9/2021 | Corrections Issued | BRENDAN LOONEY |
| METHANE-Barrier | 9/9/2021 | Approved | BRENDAN LOONEY |
| METHANE-Subgrade | 9/9/2021 | Approved | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 9/14/2021 | Approved | SHAVONNE ESPINOZA |
| Footing/Foundation/Slab | 9/16/2021 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2021 | Partial Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 10/1/2021 | Corrections Issued | BRENDAN LOONEY |
| Green Building Rough | 10/1/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| METHANE-Rough | 10/1/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 10/1/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Shower Pan | 10/1/2021 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 10/7/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Wood Frame | 10/7/2021 | Corrections Issued | BRENDAN LOONEY |
| Drywall Nailing | 10/13/2021 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 10/13/2021 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 10/18/2021 | Approved | RYAN SALAZAR |
| Wood Frame | 10/18/2021 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 10/19/2021 | Approved | RYAN SALAZAR |
| Drywall Nailing | 10/22/2021 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 11/18/2021 | Approved | ENRIQUE MIRELES |
| Final | 11/18/2021 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 11/18/2021 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 11/18/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 11/18/2021 | Approved | ENRIQUE MIRELES |
| Final | 11/24/2021 | Corrections Issued | BOBBY KEY |
| Final | 1/27/2023 | OK to Issue CofO | BOBBY KEY |