14617 W ALBERS ST 91411

Certificate Information: 14617 W ALBERS ST 91411

Application / Permit
21014-20000-02358
Plan Check / Job No.
B21VN05737
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
29'-10" X 28' IRREGULAR SHAPE ADDITION AND INTERIOR REMODEL TO THE (E) SFD WITH THE (N) 25'9' X 9'-11" DECK LESS THAN 30" IN HEIGHT. ALL WORK PER ENGINEER.
Permit Issued
Issued on 6/30/2021
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2021 APPLICANT
Assigned to Plan Check Engineer 5/18/2021 PARISA ZAHABI
Corrections Issued 5/18/2021 PARISA ZAHABI
Applicant returned to address corrections 6/16/2021 PARISA ZAHABI
Plan Check Approved 6/22/2021 PARISA ZAHABI
Building Plans Picked Up 6/24/2021 APPLICANT
Issued 6/30/2021 APPLICANT
CofO in Progress 7/6/2022 JACK KARGODORIAN
CofO Issued 7/23/2022 MICHAEL SMITH
Permit Finaled 7/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/1/2021 DAGOVERTO GUERRERO
Roof/Waste drainage to street Cleared 6/16/2021 DAGOVERTO GUERRERO

Contact Information

Contractor Dwell Llc; Lic. No.: 1030158-B 5315 LAUREL CANYON BLVD #102      VALLEY VILLAGE, CA 91607

Inspector Information

DAVID ANDERSON, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI
RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/2/2021 Approved CHARLES POWELL
BUILDING-Rough-Frame 9/15/2021 Corrections Issued MISAEL ESPARZA
Green Building Rough 9/15/2021 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 9/15/2021 Corrections Issued MISAEL ESPARZA
Sewer 9/15/2021 Not Ready for Inspection MISAEL ESPARZA
Underground Mechanical 9/15/2021 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 9/17/2021 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 9/17/2021 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 9/23/2021 Partial Approval MISAEL ESPARZA
Insulation 9/23/2021 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 10/8/2021 Partial Approval RONALD COWAN
BUILDING-Rough-Frame 10/27/2021 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 10/27/2021 Not Ready for Inspection JACK KARGODORIAN
Floor/Roof Diaphrgm/Shear Wall 10/27/2021 Not Ready for Inspection JACK KARGODORIAN
Green Building Rough 10/27/2021 Not Ready for Inspection JACK KARGODORIAN
HVAC-Rough 10/27/2021 Not Ready for Inspection JACK KARGODORIAN
PLUMBING-Rough 10/27/2021 Approved JACK KARGODORIAN
ELECTRICAL-Rough 10/29/2021 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 10/29/2021 Approved MARK JOHNSON
HVAC-Rough 10/29/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 12/16/2021 Approved JACK KARGODORIAN
Green Building Rough 12/16/2021 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/16/2021 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 12/17/2021 Approved JACK KARGODORIAN
Green Building Rough 12/17/2021 Approved JACK KARGODORIAN
Insulation 12/21/2021 Approved JACK KARGODORIAN
Drywall Nailing 12/23/2021 Approved JACK KARGODORIAN
Shower Pan 1/26/2022 Not Ready for Inspection ASHLEY THOMPSON
Interior/Exterior Lathing 1/28/2022 Partial Approval JACK KARGODORIAN
Shower Pan 1/28/2022 Not Ready for Inspection JACK KARGODORIAN
Interior/Exterior Lathing 1/31/2022 Approved ASHLEY THOMPSON
Shower Pan 1/31/2022 Approved ASHLEY THOMPSON
Final 3/31/2022 Corrections Issued JACK KARGODORIAN
Green Building Final 3/31/2022 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 3/31/2022 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 3/31/2022 Approved JACK KARGODORIAN
Final 5/9/2022 Not Ready for Inspection JACK KARGODORIAN
Green Building Final 5/9/2022 Approved JACK KARGODORIAN
Final 7/6/2022 OK to Issue CofO JACK KARGODORIAN