3459 N ARDSLEY PL 91436
Certificate Information: 3459 N ARDSLEY PL 91436
- Application / Permit
- 21014-20000-02341
- Plan Check / Job No.
- B21VN05695
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL TO THE (E)SINGLE FAMILY DWELLING FOR TWO BATHROOMS, LAUNDRY ROOM, KITCHEN AND CREATE A NEW BEDROOM AND BATHROOM.
- Permit Issued
- Issued on 9/24/2021
- Issuing Office
- Current Status
- Permit Finaled on 2/16/2023
Permit Application Status History
| Submitted | 5/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/14/2021 | SARKIS HARABEDIAN |
| Corrections Issued | 5/15/2021 | SARKIS HARABEDIAN |
| Plan Check Approved | 9/23/2021 | SARKIS HARABEDIAN |
| Issued | 9/24/2021 | APPLICANT |
| Building Plans Picked Up | 9/27/2021 | APPLICANT |
| Permit Finaled | 2/7/2023 | VINCENT HANLEY |
| CofO in Progress | 2/7/2023 | VINCENT HANLEY |
| No Progress | 2/8/2023 | SEAN WIRCH |
Permit Application Clearance Information
| Sewer availability | Cleared | 8/23/2021 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | DAGOVERTO GUERRERO |
| Specific Plan | Cleared | 8/31/2021 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shakiban,, George; Lic. No.: C39908 | 23945 CALABASAS RD STE 101 CALABASAS, CA 91302 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/19/2021 | Partial Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 5/23/2022 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/15/2022 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2022 | Approved | VINCENT HANLEY |
| Gas Test | 9/15/2022 | Partial Approval | VINCENT HANLEY |
| Green Building Rough | 9/15/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 9/15/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 9/15/2022 | Approved | VINCENT HANLEY |
| Insulation | 10/4/2022 | Approved | VINCENT HANLEY |
| Drywall Nailing | 10/13/2022 | Approved | JESUS PINEDA |
| Shower Pan | 11/7/2022 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/16/2022 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 2/1/2023 | Approved | VINCENT HANLEY |
| Final | 2/1/2023 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 2/1/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/1/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/1/2023 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 2/1/2023 | Approved | VINCENT HANLEY |
| Final | 2/7/2023 | Permit Finaled | VINCENT HANLEY |