11803 W SNELLING ST 91352
Certificate Information: 11803 W SNELLING ST 91352
- Application / Permit
- 21014-20000-02339
- Plan Check / Job No.
- B21VN05692
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, REMOVE (E) KITCHEN, 34'-4" X 35'-9" (IRERGULAR SHAPED ) ADDITION TO (E) SFD.
- Permit Issued
- Issued on 2/14/2022
- Issuing Office
- Current Status
- Issued on 2/14/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2021 | ARTIN ZARUKIAN |
| Corrections Issued | 5/22/2021 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 5/26/2021 | APPLICANT |
| Plan Check Approved | 12/8/2021 | ARTIN ZARUKIAN |
| Issued | 2/14/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/30/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 9/30/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 10/28/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/1/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 2/16/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 3/22/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 3/22/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Wood Frame | 3/22/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 3/23/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 4/12/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/12/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 4/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/26/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/26/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 4/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 5/3/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 5/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/11/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 5/26/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 12/30/2022 | Corrections Issued | MATTHEW NELSON |
| Green Building Final | 12/30/2022 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 12/30/2022 | SGSOV Approved | MATTHEW NELSON |
| Smoke Detectors | 12/30/2022 | Approved | MATTHEW NELSON |