6441 N AGNES AVE 91606

Certificate Information: 6441 N AGNES AVE 91606

Application / Permit
21014-20000-02334
Plan Check / Job No.
B21VN05665
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 18' X 20' (E) DETACHED GARAGE AND 16' X 20' REC. ROOM INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (e). ADD 11'-8" X 11'-8" ATTACHED PATIO COVER. ALL WORK PER WFPP.
Permit Issued
Issued on 6/8/2021
Issuing Office
Current Status
CofO Issued on 10/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2021 APPLICANT
Assigned to Plan Check Engineer 5/14/2021 RAPHAEL ROSAS
Corrections Issued 5/16/2021 RAPHAEL ROSAS
Issued 6/8/2021 APPLICANT
Building Plans Picked Up 6/22/2021 APPLICANT
CofO in Progress 10/25/2021 ARAM AVEDISIAN
Permit Finaled 10/26/2021 MICHAEL SMITH
CofO Issued 10/26/2021 MICHAEL SMITH
Permit Finaled 10/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 5/24/2021 CARLOS AGUILERA
Construction near power lines Cleared 5/24/2021 WALTER RAMIREZ
Roof/Waste drainage to street Cleared 5/24/2021 CARLOS AGUILERA
Sewer availability Cleared 5/24/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/25/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/29/2021 Partial Inspection ARAM AVEDISIAN
Pre-Inspection 7/7/2021 Approved DANIEL DREW
Pre-Inspection 7/23/2021 Partial Approval DANIEL DREW
Deputy Drilled-In Anchors 7/29/2021 Conditional Approval ALAN MORELOS
Excavation/Setback/Form/Re-Bar 8/3/2021 Approved DANIEL DREW
ELECTRICAL-Rough 8/10/2021 Approved DANIEL DREW
HVAC-Rough 8/10/2021 Approved DANIEL DREW
PLUMBING-Rough 8/10/2021 Approved DANIEL DREW
Insulation 8/12/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 8/16/2021 Approved DANIEL DREW
Drywall Nailing 8/18/2021 Approved ALIZAH MAYAGOITIA
Shower Pan 9/3/2021 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/8/2021 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 10/8/2021 No Access for Inspection GREGG CUMMINGS
Final 10/8/2021 No Access for Inspection GREGG CUMMINGS
Footing/Foundation/Slab 10/8/2021 No Access for Inspection GREGG CUMMINGS
Green Building Final 10/8/2021 No Access for Inspection GREGG CUMMINGS
Green Building Rough 10/8/2021 No Access for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 10/8/2021 SGSOV Not Ready GREGG CUMMINGS
Smoke Detectors 10/8/2021 No Access for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 10/13/2021 Approved DANIEL DREW
Final 10/13/2021 Not Ready for Inspection DANIEL DREW
Footing/Foundation/Slab 10/13/2021 Approved DANIEL DREW
Green Building Final 10/13/2021 Corrections Issued DANIEL DREW
Green Building Rough 10/13/2021 Approved DANIEL DREW
SGSOV-Seismic Gas S/O Valve 10/13/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 10/13/2021 Approved DANIEL DREW
Final 10/19/2021 Corrections Issued DANIEL DREW
Green Building Final 10/19/2021 Corrections Issued DANIEL DREW
Final 10/25/2021 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 10/25/2021 Approved ARAM AVEDISIAN