196 N THURSTON AVE 90049

Certificate Information: 196 N THURSTON AVE 90049

Application / Permit
21014-20000-02329
Plan Check / Job No.
B21VN05654
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL & 1,420 SQ. FT. 1ST AND 2ND FLOOR ADDITION WITH 261 SQ. FT. BALCONY ADDITION TO THE (E) IRREGULAR SHAPED SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/9/2022
Issuing Office
Current Status
CofO Issued on 4/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2021 APPLICANT
Assigned to Plan Check Engineer 7/1/2021 COLIN LOREDO
Corrections Issued 7/8/2021 COLIN LOREDO
Quality Review Completed 7/9/2021 OMID HEDAYAT
Building Plans Picked Up 7/13/2021 APPLICANT
Plan Check Approved 1/13/2022 COLIN LOREDO
Issued 2/9/2022 APPLICANT
Permit Finaled 4/23/2024 DANIEL ORRANTE
CofO Issued 4/23/2024 DANIEL ORRANTE
Permit Finaled 4/23/2024 DANIEL ORRANTE

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 7/20/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 7/20/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 7/20/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 7/20/2021 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 7/20/2021 DENNIS BRAGIN
Sewer availability Cleared 7/20/2021 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 8/10/2021 DENNIS BRAGIN
Hydrant and Access approval Cleared 9/25/2021 GILBERT URREA
Low Impact Development Cleared 10/19/2021 SAHIL SHARMA
Roof/Waste drainage to street Cleared 10/20/2021 DENNIS BRAGIN
GPI Written Notices Cleared 1/13/2022 COLIN LOREDO
Grading Pre-Inspection Cleared 1/13/2022 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 21126 MERRIDY STREET      CHATSWORTH, CA 91311

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/4/2022 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 4/5/2022 Approved CARLOS MATAMOROS
PLUMBING-Rough 4/6/2022 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 4/11/2022 Partial Approval CARLOS MATAMOROS
Deputy Drilled-In Anchors 4/20/2022 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/20/2022 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 4/25/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 6/3/2022 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 6/10/2022 Not Ready for Inspection CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 6/21/2022 Approved CARLOS MATAMOROS
HVAC-Rough 6/21/2022 Approved CARLOS MATAMOROS
PLUMBING-Rough 6/21/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 7/1/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Rough 7/1/2022 Not Ready for Inspection CHRISTOPHER WILSON
Shower Pan 7/1/2022 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 7/1/2022 Not Ready for Inspection CHRISTOPHER WILSON
BUILDING-Rough-Frame 7/5/2022 Corrections Issued CARLOS MATAMOROS
Green Building Rough 7/5/2022 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 7/5/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 7/8/2022 Approved CARLOS MATAMOROS
Shower Pan 7/8/2022 Approved CARLOS MATAMOROS
Insulation 7/18/2022 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 7/18/2022 Not Ready for Inspection CARLOS MATAMOROS
Drywall Nailing 7/25/2022 Approved PATRICK QUALEY
Interior/Exterior Lathing 8/1/2022 Conditional Approval CLAYTON GRAHAM
ELECTRICAL-Final 3/24/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Final 3/24/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 3/24/2023 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 3/29/2023 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Final 4/3/2023 Not Ready for Inspection CARLOS MATAMOROS
Final 4/3/2023 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 4/3/2023 Approved CARLOS MATAMOROS
Green Building Final 4/3/2023 Approved CARLOS MATAMOROS
HVAC-Final 4/3/2023 Approved CARLOS MATAMOROS
PLUMBING-Final 4/3/2023 Approved CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/3/2023 SGSOV Not Ready CARLOS MATAMOROS
Smoke Detectors 4/3/2023 Approved CARLOS MATAMOROS
ELECTRICAL-Final 4/4/2023 Approved CARLOS MATAMOROS
HVAC-Final 4/4/2023 Approved CARLOS MATAMOROS
PLUMBING-Final 4/4/2023 Approved CARLOS MATAMOROS
Final 2/2/2024 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 2/2/2024 SGSOV Not Ready CARLOS MATAMOROS
Special/Order Compliance 2/6/2024 Corrections Issued CARLOS MATAMOROS
Final 4/19/2024 Partial Approval CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 4/19/2024 SGSOV Approved CARLOS MATAMOROS