5649 N COLBATH AVE 91401
Certificate Information: 5649 N COLBATH AVE 91401
- Application / Permit
- 21014-20000-02327
- Plan Check / Job No.
- B21VN05653
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 12'x6"x15'-8" IRREGULAR SHAPED ADDITION
- Permit Issued
- Issued on 6/18/2021
- Issuing Office
- Current Status
- CofO Issued on 11/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2021 | ALYSSA N NARCISO |
| Corrections Issued | 6/7/2021 | ALYSSA N NARCISO |
| Plan Check Approved | 6/18/2021 | ALYSSA N NARCISO |
| Issued | 6/18/2021 | APPLICANT |
| Building Plans Picked Up | 6/18/2021 | APPLICANT |
| CofO in Progress | 11/16/2022 | RICHARD DOCKUS |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
| CofO Issued | 11/19/2022 | MICHAEL SMITH |
| Permit Finaled | 11/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/9/2021 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 6/9/2021 | LEE GUILBEAUX |
| Sewer availability | Cleared | 6/9/2021 | LEE GUILBEAUX |
Contact Information
| Contractor | Your Favorite Contractor Inc; Lic. No.: 851344-B | 18375 VENTURA BLVD #402 TARZANA, CA 91356 |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/12/2021 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 7/15/2021 | Partial Approval | RICHARD DOCKUS |
| PLUMBING-Rough | 7/15/2021 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2021 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 7/26/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Rough | 7/29/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2021 | Partial Approval | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 7/29/2021 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 8/2/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 8/2/2021 | Approved | JENNIFER RABUCHIN |
| HVAC-Rough | 8/2/2021 | Partial Approval | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/2/2021 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2021 | Approved | ALAN MORELOS |
| Insulation | 8/5/2021 | Approved | ALAN MORELOS |
| BUILDING-Rough-Frame | 8/11/2021 | Approved | RYAN SALAZAR |
| Drywall Nailing | 8/11/2021 | Approved | RYAN SALAZAR |
| Final | 11/15/2022 | OK to Issue CofO | RICHARD DOCKUS |
| Green Building Final | 11/15/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 11/15/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 11/15/2022 | Approved | RICHARD DOCKUS |